135 23rd Av
San Francisco permit 202504013449 · Outer Richmond
Voluntary soft story retrofit with added footings under (e) foundation for 8' x 12' (e) addition.
- Filed
- May 6, 2025
- Issued
- Aug 1, 2025 (3 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 9 stops across 2 departments
- Comments issued
- 3 times, by Permit Center, Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Mar 28, 2025 | Apr 16, 2025 | Issued Comments |
Central Permit Bureau Building Inspection · CPB | Apr 1, 2025 | May 6, 2025 | Administrative |
Permit Center Permit Center · PERMIT-CTR | Apr 17, 2025 | Apr 29, 2025 | Approved |
Building plan review Building Inspection · BLDG | May 6, 2025 | Jun 24, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | May 6, 2025 | Jun 24, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | May 6, 2025 | Jul 25, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Jul 23, 2025 | Jul 23, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jul 23, 2025 | Jul 23, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 25, 2025 | Aug 1, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $10,000
| Name | Role | License on permit |
|---|---|---|
| Majd Sameer Mniarji | Engineer | C-93049 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2022