Rear bldg: legalize one (e) unit at first flr of the (e) northwest single family bldg. the unit will be 1-bedroom unit w/ a kitchen and a bath. no work proposed on other, the legalized unit to be provided with nfpa 13r automatice fire sprinkler system under separate permit.
- Filed
- Apr 23, 2025
- Issued
- Jan 14, 2026 (9 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 34 stops across 6 departments
- Comments issued
- 4 times, by Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Mar 29, 2025 | Apr 16, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 2, 2025 | Apr 23, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Apr 23, 2025 | Jun 3, 2025 | Approved |
Building plan review Building Inspection · BLDG | Apr 23, 2025 | May 20, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 23, 2025 | May 11, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Apr 23, 2025 | May 2, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 23, 2025 | Apr 28, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Apr 23, 2025 | Apr 30, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Apr 23, 2025 | Apr 29, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Apr 23, 2025 | Dec 11, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Jul 28, 2025 | Jul 28, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Aug 15, 2025 | Aug 28, 2025 | Approved |
Building plan review Building Inspection · BLDG | Aug 15, 2025 | Aug 20, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 15, 2025 | Aug 18, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Aug 15, 2025 | Aug 19, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 15, 2025 | Aug 18, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Aug 15, 2025 | Sep 17, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Aug 15, 2025 | Aug 15, 2025 | Approved |
Zoning review Planning · CP-ZOC | Sep 25, 2025 | Sep 26, 2025 | Approved |
Building plan review Building Inspection · BLDG | Sep 25, 2025 | Oct 20, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 25, 2025 | Oct 2, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Sep 25, 2025 | Oct 15, 2025 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Sep 25, 2025 | Sep 29, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Sep 25, 2025 | Oct 9, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 25, 2025 | Sep 26, 2025 | Approved |
Development fee collection Building Inspection · DFCU | Oct 20, 2025 | Dec 10, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Oct 28, 2025 | Dec 10, 2025 | Approved |
Building plan review Building Inspection · BLDG | Oct 28, 2025 | Nov 7, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 28, 2025 | Oct 31, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Oct 28, 2025 | Nov 14, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 28, 2025 | Oct 29, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Oct 28, 2025 | Nov 10, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 28, 2025 | Oct 30, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 11, 2025 | Jan 14, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $150,000
| Name | Role | License on permit |
|---|---|---|
| John Taylor Hood Janes Street Architects | Architect | C-14187 |
| Donald David Double D Enginneering, Inc | Engineer | 3928 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025