221 Main St
San Francisco permit 202504043725 · Financial District/South Beach
Priority processing per ab-004.t.i of suites 104 & 250 on 1st fl & 2nd fl to create space for non-profit,private school for for grade 6-12,interior demolition of interior,including portion of 2nd fl structural slab for(n) stair opening,construction of(n)paritions doors,ceilings,finishes,fixtures.
- Filed
- Apr 15, 2025
- Issued
- Jul 10, 2025 (3 months after filing)
- Completed
- Jan 7, 2026 (6 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 25 stops across 6 departments
- Comments issued
- 7 times, by Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Mar 26, 2025 | Apr 9, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 10, 2025 | Apr 15, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Apr 15, 2025 | May 8, 2025 | Approved |
Building plan review Building Inspection · BLDG | Apr 15, 2025 | May 29, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Apr 15, 2025 | May 28, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 15, 2025 | May 22, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Apr 15, 2025 | May 3, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 15, 2025 | Apr 23, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 15, 2025 | Apr 23, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Apr 15, 2025 | Jul 7, 2025 | Administrative |
Electrical plan review Building Inspection · MECH-E | May 2, 2025 | May 8, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | May 14, 2025 | May 15, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | May 14, 2025 | May 19, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 14, 2025 | May 14, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jun 20, 2025 | Jun 27, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 23, 2025 | Jun 23, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Jun 25, 2025 | Jun 25, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 26, 2025 | Jun 27, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jun 27, 2025 | Jun 27, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Jun 27, 2025 | Jun 27, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 27, 2025 | Jun 27, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jul 1, 2025 | Jul 1, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jul 2, 2025 | Jul 2, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 2, 2025 | Jul 3, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 7, 2025 | Jul 10, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $10,000,000
| Name | Role | License on permit |
|---|---|---|
| Steven Huegli Jensen Architects | Architect | C32013 |
| Leo Panian Tipping Structural Engineers | Engineer | S4526 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2023