1155 Harrison St
San Francisco permit 202504083912 · South of Market
At&t wireless facility: remove 4 panel antennas; relocate 1 antenna on (n) pipe mast; add 2 panel & 3 air antennas; relocate 5 radios; remove 3 dc-6 & 1 dc6 w/ 2 power & 1 fiber cable; install 3 new dc9 surge arrestors, power & fiber trunks; remove 1 3106 rbs cabinet
- Filed
- Apr 8, 2025
- Issued
- Sep 17, 2025 (5 months after filing)
- Completed
- Feb 10, 2026 (5 months after issuance)
- Review stops
- 12 stops across 5 departments
- Comments issued
- 3 times, by Planning, Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Apr 8, 2025 | Apr 8, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Apr 8, 2025 | Apr 8, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Apr 10, 2025 | Apr 10, 2025 | Issued Comments |
Public health review Public Health · HEALTH | May 7, 2025 | May 7, 2025 | Approved |
Zoning review Planning · CP-ZOC | May 8, 2025 | May 8, 2025 | Approved |
Building plan review Building Inspection · BLDG | May 8, 2025 | May 8, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | May 8, 2025 | May 8, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | May 8, 2025 | May 8, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 8, 2025 | May 8, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | May 8, 2025 | May 8, 2025 | Approved |
Fire prevention review Fire Department · SFFD | May 8, 2025 | May 8, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 17, 2025 | Sep 17, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $60,000
| Name | Role | License on permit |
|---|---|---|
| Seung Kun Oh | Engineer | S6836 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026