255 California St
San Francisco permit 202504083979 · Financial District/South Beach
4th floor: tenant improvement work on 2,878 sq ft of total floor area. new wall, power, lighting and finishes.
- Filed
- Apr 8, 2025
- Issued
- Jun 13, 2025 (2 months after filing)
- Completed
- Nov 19, 2025 (5 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2025 were typically issued within 1 month (median of 5,178 issued permits).
- Review stops
- 11 stops across 4 departments
- Comments issued
- Once, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Apr 8, 2025 | Apr 8, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Apr 9, 2025 | Apr 9, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 10, 2025 | Apr 10, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Apr 10, 2025 | Apr 10, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Apr 10, 2025 | Apr 10, 2025 | Approved |
Building plan review Building Inspection · BLDG | Apr 29, 2025 | Apr 29, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 29, 2025 | Apr 29, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Apr 29, 2025 | Apr 29, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 29, 2025 | Apr 29, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jun 13, 2025 | Jun 13, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jun 13, 2025 | Jun 13, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $450,000
| Name | Role | License on permit |
|---|---|---|
| Nelson Algaze Saa | Architect | C21090 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Nov 2025