729 Kirkwood Av
San Francisco permit 202504094052 · Bayview Hunters Point
Prop h:renovation of outdoor play area including:protection of all(e)canopy trees;demolition & removal of existing exterior paving surfaces & the corresponding surface base course.demolition & removal of (e)playground climbing structures;demolition & removal of(e)onsite chain link fencing.
- Filed
- Apr 9, 2025
- Issued
- Nov 6, 2025 (7 months after filing)
- Completed
- May 29, 2026 (7 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2025 were typically issued within 1 month (median of 5,178 issued permits).
- Review stops
- 30 stops across 5 departments
- Comments issued
- 10 times, by Planning, Building Inspection, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 9, 2025 | Apr 9, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Apr 9, 2025 | Apr 14, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Apr 9, 2025 | Apr 25, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 9, 2025 | Apr 14, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Apr 9, 2025 | Apr 17, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 9, 2025 | Apr 16, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 9, 2025 | Apr 22, 2025 | Not Applicable |
Permit Processing Center Building Inspection · PPC | Apr 9, 2025 | Sep 22, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Jun 18, 2025 | Jun 23, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 18, 2025 | Jun 18, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 18, 2025 | Jun 23, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 20, 2025 | Jun 20, 2025 | Not Applicable |
Building plan review quality control Building Inspection · BLDG-QC | Jun 25, 2025 | Jun 25, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 26, 2025 | Jun 26, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Jun 27, 2025 | Jun 27, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Aug 18, 2025 | Aug 18, 2025 | Approved |
Building plan review Building Inspection · BLDG | Aug 18, 2025 | Aug 19, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Aug 18, 2025 | Aug 22, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 20, 2025 | Aug 20, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 20, 2025 | Aug 20, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Aug 21, 2025 | Aug 21, 2025 | Not Applicable |
Mechanical and energy plan review Building Inspection · MECH | Aug 22, 2025 | Aug 26, 2025 | Approved |
Building plan review Building Inspection · BLDG | Sep 8, 2025 | Sep 8, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 8, 2025 | Sep 8, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 8, 2025 | Sep 8, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Sep 9, 2025 | Sep 9, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 9, 2025 | Sep 9, 2025 | Not Applicable |
Zoning review Planning · CP-ZOC | Sep 17, 2025 | Sep 17, 2025 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Sep 22, 2025 | Sep 22, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Sep 22, 2025 | Nov 6, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $785,000
| Name | Role | License on permit |
|---|---|---|
| Christopher J Dorman Dorman Assoc | Authorized agent-others | C28300 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2023