1011 Garfield St
San Francisco permit 202504094065 · Oceanview/Merced/Ingleside
Prop h: project involves a renovation of the children's play area and access/egress to the playground from the exterior sidewalk.this includes the removal of the(e)ramp,including handrails & landings,& a portion of the(e)fence adjacent to the ramp.new accessible walkway from the sidewalk entrance
- Filed
- Apr 9, 2025
- Issued
- Feb 24, 2026 (11 months after filing)
- Completed
- Oct 30, 2026 (8 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2025 were typically issued within 1 month (median of 5,178 issued permits).
- Review stops
- 21 stops across 5 departments
- Comments issued
- 8 times, by Planning, Building Inspection, Fire Department, Public Works, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 9, 2025 | Apr 9, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Apr 9, 2025 | Apr 14, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Apr 9, 2025 | Apr 25, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 9, 2025 | Apr 14, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Apr 9, 2025 | Apr 17, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 9, 2025 | Apr 18, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Apr 9, 2025 | Apr 22, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Apr 9, 2025 | Feb 2, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Aug 7, 2025 | Aug 12, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 7, 2025 | Aug 7, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 7, 2025 | Aug 7, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Aug 8, 2025 | Aug 8, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Aug 8, 2025 | Aug 8, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 8, 2025 | Aug 8, 2025 | Not Applicable |
Zoning review Planning · CP-ZOC | Aug 22, 2025 | Aug 22, 2025 | Approved |
Building plan review Building Inspection · BLDG | Aug 22, 2025 | Aug 22, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 22, 2025 | Aug 25, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Aug 22, 2025 | Aug 22, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 25, 2025 | Aug 25, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Feb 2, 2026 | Feb 2, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 2, 2026 | Feb 24, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $290,000
| Name | Role | License on permit |
|---|---|---|
| Christopher J Dorman Dorman Assoc | Architect | C28300 |
| Christopher James Wood Luk And Associates | Engineer | C72184 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2019