3845 26th St

San Francisco permit 202504114247 · Noe Valley

AdditionFull plan reviewIssued
Street view · Mar 2025
Google Street View of 3845 26th St, Mar 2025
Scope of work
As written on the permit application.

Horizontal addition to (e) 2-unit residential bldg. new front windows. new front doors at entry, in-kind. renovation throughout levels 1-4. new stair core. new rear decks. 4-new dormers at level 4 with skylight. new sprinkler throughout levels 1-4. renovate bathrooms and 2-kitchens. new rear windows

Timeline
Key dates from the city record.
Filed
Apr 24, 2025
Issued
Aug 13, 2025 (4 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
22 stops across 6 departments
Comments issued
7 times, by Building Inspection, Fire Department, Public Works
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Apr 24, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Apr 25, 2025Administrative

Zoning review

Planning · CP-ZOC

May 29, 2025Approved

Building plan review

Building Inspection · BLDG

Jun 8, 2025Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jun 11, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

May 19, 2025Issued Comments

Street use and mapping

Public Works · DPW-BSM

Apr 30, 2025Issued Comments

Urban forestry

Public Works · DPW-BUF

Jun 6, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Apr 28, 2025Approved

Permit Processing Center

Building Inspection · PPC

Aug 6, 2025Administrative

Street use and mapping

Public Works · DPW-BSM

May 20, 2025Approved

Zoning review

Planning · CP-ZOC

Jul 1, 2025Approved

Building plan review

Building Inspection · BLDG

Jul 16, 2025Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jul 17, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

Jul 2, 2025Issued Comments

Street use and mapping

Public Works · DPW-BSM

Jul 2, 2025Approved

Urban forestry

Public Works · DPW-BUF

Jul 15, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jul 9, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Jul 18, 2025Approved

Building plan review

Building Inspection · BLDG

Jul 22, 2025Approved

Fire prevention review

Fire Department · SFFD

Aug 5, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Aug 13, 2025Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$980,275
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Peter Yen Liang

Blue Truck Studio

ArchitectC-37831
Jason R Powers

Zfa Structural Engineers

Engineer76130
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202504114247 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record