2770 Green St
San Francisco permit 202504154412 · Marina
Rear horizontal addition at 1st-4th floors. addition of basement level at rear. remove pitched roofs behind facade and replace with low pitched roof above (4th floor). interior remodel at all levels. enlarge garage. new elevator. structural upgrade
- Filed
- May 28, 2025
- Issued
- Nov 17, 2025 (6 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 66 stops across 6 departments
- Comments issued
- 18 times, by Permit Center, Building Inspection, Fire Department, Public Works
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Apr 8, 2025 | Apr 25, 2025 | Issued Comments |
Central Permit Bureau Building Inspection · CPB | Apr 17, 2025 | May 28, 2025 | Administrative |
Permit Center Permit Center · PERMIT-CTR | May 15, 2025 | May 27, 2025 | Approved |
Zoning review Planning · CP-ZOC | May 28, 2025 | May 30, 2025 | Approved |
Building plan review Building Inspection · BLDG | May 28, 2025 | Jun 20, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | May 28, 2025 | Jul 21, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | May 28, 2025 | May 30, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | May 28, 2025 | May 30, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | May 28, 2025 | Jul 15, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | May 28, 2025 | Jun 3, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | May 28, 2025 | Nov 6, 2025 | Administrative |
Building plan review quality control Building Inspection · BLDG-QC | Jun 17, 2025 | Jun 17, 2025 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Jun 23, 2025 | Jun 23, 2025 | Approved |
Building plan review Building Inspection · BLDG | Sep 11, 2025 | Sep 16, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Sep 19, 2025 | Sep 19, 2025 | Approved |
Building plan review Building Inspection · BLDG | Oct 15, 2025 | Oct 15, 2025 | Issued Comments |
Building plan review quality control Building Inspection · BLDG-QC | Oct 15, 2025 | Oct 15, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Oct 16, 2025 | Oct 20, 2025 | Approved |
Zoning review Planning · CP-ZOC | Oct 17, 2025 | Oct 17, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Oct 17, 2025 | Oct 23, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 22, 2025 | Oct 27, 2025 | Approved |
Building plan review Building Inspection · BLDG | Oct 28, 2025 | Oct 28, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Oct 29, 2025 | Oct 29, 2025 | Issued Comments |
Building plan review quality control Building Inspection · BLDG-QC | Oct 30, 2025 | Oct 30, 2025 | Approved |
Building plan review Building Inspection · BLDG | Nov 4, 2025 | Nov 4, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 5, 2025 | Nov 6, 2025 | Approved |
Development fee collection Building Inspection · DFCU | Nov 6, 2025 | Nov 6, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Nov 6, 2025 | Nov 17, 2025 | Administrative |
Addendum 1: Foundations, structural superstructure
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Apr 28, 2026 | May 18, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | May 19, 2026 | May 19, 2026 | Administrative |
Building plan review Building Inspection · BLDG | May 19, 2026 | Jul 17, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | May 19, 2026 | Jul 14, 2026 | Not Applicable |
Fire prevention review Fire Department · SFFD | May 19, 2026 | May 29, 2026 | Not Applicable |
Permit Processing Center Building Inspection · PPC | May 19, 2026 | Sep 22, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Aug 5, 2026 | Aug 5, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Aug 20, 2026 | Aug 25, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 9, 2026 | Sep 9, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 11, 2026 | Sep 11, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 14, 2026 | Sep 16, 2026 | Approved |
Development fee collection Building Inspection · DFCU | Sep 16, 2026 | Sep 16, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | Sep 22, 2026 | Sep 24, 2026 | Administrative |
Addendum 2: Architectural, mechanical, greenpoint energy
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Feb 5, 2026 | Feb 12, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 13, 2026 | Mar 3, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Mar 3, 2026 | Mar 4, 2026 | Approved |
Building plan review Building Inspection · BLDG | Mar 3, 2026 | Apr 17, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 3, 2026 | Apr 10, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 3, 2026 | Mar 6, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Mar 3, 2026 | Mar 11, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Mar 3, 2026 | Apr 4, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 3, 2026 | Mar 4, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Mar 3, 2026 | Sep 11, 2026 | Administrative |
Fire prevention review Fire Department · SFFD | May 22, 2026 | May 22, 2026 | Approved-Stipulated |
Fire prevention review Fire Department · SFFD | Aug 4, 2026 | Aug 4, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Aug 5, 2026 | Aug 11, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 10, 2026 | Aug 10, 2026 | Approved |
Building plan review Building Inspection · BLDG | Aug 20, 2026 | Aug 25, 2026 | Approved |
Zoning review Planning · CP-ZOC | Aug 25, 2026 | Aug 25, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Aug 25, 2026 | Sep 4, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 25, 2026 | Aug 27, 2026 | Approved |
Zoning review Planning · CP-ZOC | Sep 4, 2026 | Sep 4, 2026 | Approved |
Building plan review Building Inspection · BLDG | Sep 4, 2026 | Sep 8, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 4, 2026 | Sep 11, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Sep 4, 2026 | Sep 8, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Sep 4, 2026 | Sep 9, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 4, 2026 | Sep 9, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 11, 2026 | Sep 22, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $2,518,206
| Name | Role | License on permit |
|---|---|---|
| Earle Edward Weiss E.E. Weiss Architects, Inc. | Architect | C22416 |
| Erwin J O'toole Shore Cal | Engineer | C80734 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jun 2025