3183 Cesar Chavez St
San Francisco permit 202504154493 · Bernal Heights
Remodel ground floor by adding office and kitchenette, fully remodel second and third floors. exterior work are including skylights, windows, exterior doors, paint and patch stucco, entry gate, entry tile, and lighting.
- Filed
- May 4, 2025
- Issued
- Sep 4, 2025 (4 months after filing)
- Completed
- Jun 3, 2026 (9 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 25 stops across 6 departments
- Comments issued
- 7 times, by Building Inspection, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Apr 14, 2025 | Apr 29, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | May 5, 2025 | May 5, 2025 | Administrative |
Zoning review Planning · CP-ZOC | May 5, 2025 | May 30, 2025 | Approved |
Building plan review Building Inspection · BLDG | May 5, 2025 | Jun 2, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | May 5, 2025 | Jun 2, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 5, 2025 | May 29, 2025 | Approved |
Fire prevention review Fire Department · SFFD | May 5, 2025 | May 7, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | May 5, 2025 | May 7, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | May 5, 2025 | Jun 3, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 5, 2025 | May 14, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | May 5, 2025 | Aug 28, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jul 7, 2025 | Jul 7, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jul 7, 2025 | Jul 9, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jul 7, 2025 | Jul 14, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jul 10, 2025 | Jul 15, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jul 10, 2025 | Jul 14, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jul 15, 2025 | Jul 15, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 4, 2025 | Aug 5, 2025 | Approved-Stipulated |
Zoning review Planning · CP-ZOC | Aug 5, 2025 | Aug 25, 2025 | Approved |
Building plan review Building Inspection · BLDG | Aug 5, 2025 | Aug 5, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Aug 5, 2025 | Aug 5, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 5, 2025 | Aug 6, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Aug 5, 2025 | Aug 28, 2025 | Approved |
Development fee collection Building Inspection · DFCU | Aug 28, 2025 | Aug 28, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Aug 28, 2025 | Sep 4, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $700,000
| Name | Role | License on permit |
|---|---|---|
| Chester Jay M Gatdula Bluejay Structures | Engineer | C87161 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Oct 2017