108 Chattanooga St

San Francisco permit 202504154498 · Noe Valley

AdditionFull plan reviewIssued
Street view · Mar 2025
Google Street View of 108 Chattanooga St, Mar 2025
Scope of work
As written on the permit application.

Rear horiz. addition & infill @ 2nd & 3rd flrs; expansion of conditioned living space to 1st flr toliving space to the 1st flr to include guest/exercise rm & bath; reconfigure rear kitchen & dining areas & convert full bath to powder rm @ 2nd fl; renova & reconfigure 3rd flr bedrms & bath to add.

Timeline
Key dates from the city record.
Filed
Oct 14, 2025
Issued
May 14, 2026 (7 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
42 stops across 6 departments
Comments issued
9 times, by Permit Center, Building Inspection, Public Works
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Apr 30, 2025Issued Comments

Permit Center

Permit Center · PERMIT-CTR

Sep 25, 2025Issued Comments

Permit Center

Permit Center · PERMIT-CTR

Oct 8, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Oct 15, 2025Administrative

Zoning review

Planning · CP-ZOC

Oct 17, 2025Approved

Building plan review

Building Inspection · BLDG

Nov 21, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Nov 17, 2025Administrative

Mechanical and energy plan review

Building Inspection · MECH

Nov 5, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

Oct 28, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Oct 20, 2025Issued Comments

Urban forestry

Public Works · DPW-BUF

Nov 12, 2025Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Oct 30, 2025Approved

Building inspector

Building Inspection · BID-INSP

Apr 24, 2026Approved

Permit Processing Center

Building Inspection · PPC

May 13, 2026Administrative

Zoning review

Planning · CP-ZOC

Mar 24, 2026Approved

Building plan review

Building Inspection · BLDG

Feb 9, 2026Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Feb 10, 2026Issued Comments

Fire prevention review

Fire Department · SFFD

Feb 9, 2026Approved-Stipulated

Street use and mapping

Public Works · DPW-BSM

Feb 11, 2026Approved

Urban forestry

Public Works · DPW-BUF

Feb 25, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

Feb 10, 2026Approved

Fire prevention review

Fire Department · SFFD

Feb 9, 2026Approved

Building plan review

Building Inspection · BLDG

Mar 30, 2026Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Apr 3, 2026Approved

Fire prevention review

Fire Department · SFFD

Mar 20, 2026Approved-Stipulated

Street use and mapping

Public Works · DPW-BSM

Mar 23, 2026Approved

Urban forestry

Public Works · DPW-BUF

Apr 21, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

Mar 26, 2026Approved

Fire prevention review

Fire Department · SFFD

Mar 23, 2026Approved

Zoning review

Planning · CP-ZOC

Apr 14, 2026Approved

Building plan review

Building Inspection · BLDG

Apr 15, 2026Administrative

Mechanical and energy plan review

Building Inspection · MECH

Apr 21, 2026Approved

Fire prevention review

Fire Department · SFFD

Apr 15, 2026Approved-Stipulated

Street use and mapping

Public Works · DPW-BSM

Apr 16, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

Apr 15, 2026Approved

Fire prevention review

Fire Department · SFFD

Apr 15, 2026Approved

Fire prevention review

Fire Department · SFFD

Apr 16, 2026Approved-Stipulated

Fire prevention review

Fire Department · SFFD

Apr 17, 2026Approved

Zoning review

Planning · CP-ZOC

Apr 16, 2026Approved

Building plan review

Building Inspection · BLDG

Apr 22, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

Apr 24, 2026Approved

Central Permit Bureau

Building Inspection · CPB

May 14, 2026Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$828,948
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Mark Jeffrey Topetcher

Topetcher Architectural

ArchitectC21678
Jefferson Chen

Enertia Designs

EngineerC57898
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202504154498 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record