155 Moffitt St
San Francisco permit 202504174643 · Glen Park
Demo (e) damaged rear balcony; install (n) rear balcony; demo (e) repair aged patio slab; reinforce & install new patio slab; construct (n) spiral stairway
- Filed
- Jul 18, 2025
- Issued
- Oct 30, 2025 (3 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 22 stops across 4 departments
- Comments issued
- 6 times, by Planning, Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Apr 17, 2025 | Apr 17, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Apr 17, 2025 | Apr 17, 2025 | Approved |
Intake Building Inspection · INTAKE | Jun 24, 2025 | Jun 24, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jun 24, 2025 | Jun 24, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Jun 26, 2025 | Jun 26, 2025 | Approved |
Permit Center Permit Center · PERMIT-CTR | Jul 9, 2025 | Jul 16, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 17, 2025 | Jul 21, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jul 21, 2025 | Jul 22, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Jul 21, 2025 | Aug 29, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jul 21, 2025 | Aug 29, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 21, 2025 | Aug 12, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jul 21, 2025 | Jul 22, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Jul 21, 2025 | Oct 23, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jul 22, 2025 | Jul 22, 2025 | Approved |
Building plan review Building Inspection · BLDG | Sep 26, 2025 | Sep 26, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Oct 3, 2025 | Oct 3, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Oct 15, 2025 | Oct 15, 2025 | Approved |
Building plan review Building Inspection · BLDG | Oct 15, 2025 | Oct 15, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Oct 15, 2025 | Oct 15, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 16, 2025 | Oct 21, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Oct 16, 2025 | Oct 20, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 23, 2025 | Oct 30, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $75,000
| Name | Role | License on permit |
|---|---|---|
| Amarendra Prasad Patrick Donato | Engineer | C68517 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025