683 San Jose Av
San Francisco permit 202504184740 · Bernal Heights
Proposed ground level adu (unit 2) interior addition & upper (unit 1) kitchen remodel. new foundation & lowered concrete floor slab. removed chimney for kitchen expansion. new ground level rear openings & lower yard. project seeks state adu program.
- Filed
- May 21, 2025
- Issued
- May 12, 2026 (12 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 38 stops across 6 departments
- Comments issued
- 13 times, by Permit Center, Building Inspection, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Apr 16, 2025 | Apr 29, 2025 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | May 5, 2025 | May 20, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | May 20, 2025 | May 21, 2025 | Administrative |
Zoning review Planning · CP-ZOC | May 21, 2025 | May 22, 2025 | Approved |
Building plan review Building Inspection · BLDG | May 21, 2025 | Jun 20, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | May 21, 2025 | Jun 20, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 21, 2025 | Jun 2, 2025 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | May 21, 2025 | May 29, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | May 21, 2025 | May 22, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | May 21, 2025 | Jun 26, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | May 21, 2025 | Sep 26, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | May 21, 2025 | Mar 19, 2026 | Administrative |
Fire Department housing review Fire Department · SFFD-HQ | Aug 28, 2025 | Sep 5, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Aug 29, 2025 | Sep 9, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Sep 3, 2025 | Sep 3, 2025 | Approved |
Building plan review Building Inspection · BLDG | Sep 8, 2025 | Sep 11, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Sep 8, 2025 | Sep 11, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Sep 25, 2025 | Sep 25, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 26, 2025 | Sep 26, 2025 | Approved |
Building plan review Building Inspection · BLDG | Oct 3, 2025 | Feb 24, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Oct 3, 2025 | Oct 3, 2025 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Oct 27, 2025 | Oct 30, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 27, 2025 | Oct 29, 2025 | Approved |
Zoning review Planning · CP-ZOC | Oct 28, 2025 | Oct 28, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Nov 3, 2025 | Nov 6, 2025 | Issued Comments |
Building plan review quality control Building Inspection · BLDG-QC | Feb 10, 2026 | Feb 10, 2026 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Feb 11, 2026 | Feb 24, 2026 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Feb 20, 2026 | Feb 20, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Feb 23, 2026 | Feb 23, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 23, 2026 | Feb 23, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 24, 2026 | Feb 24, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 27, 2026 | Mar 11, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Mar 11, 2026 | Mar 11, 2026 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Mar 13, 2026 | Mar 16, 2026 | Approved-Stipulated |
Fire prevention review Fire Department · SFFD | Mar 16, 2026 | Mar 16, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 19, 2026 | Mar 19, 2026 | Approved |
Development fee collection Building Inspection · DFCU | Mar 19, 2026 | Mar 19, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | Mar 19, 2026 | May 12, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $446,698
| Name | Role | License on permit |
|---|---|---|
| Sheldon Errol Eaton Vicinity Architects | Architect | C36656 |
| Della Tran Ta Structural | Engineer | 91229 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2021