2174 California St
San Francisco permit 202504184748 · Pacific Heights
One new converted adu in (e) basement of (e) multi family structure per sf state ordinance.
- Filed
- Apr 30, 2025
- Issued
- Jun 26, 2025 (2 months after filing)
- Completed
- Aug 24, 2026 (14 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 22 stops across 6 departments
- Comments issued
- 5 times, by Planning, Building Inspection, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Apr 14, 2025 | Apr 29, 2025 | Approved |
Apartment and hotel inspection Building Inspection · HIS | Apr 18, 2025 | Apr 18, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Apr 18, 2025 | Apr 30, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Apr 30, 2025 | May 2, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Apr 30, 2025 | May 12, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Apr 30, 2025 | May 12, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 30, 2025 | May 7, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Apr 30, 2025 | May 2, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 30, 2025 | May 1, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Apr 30, 2025 | Apr 30, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Apr 30, 2025 | May 1, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Apr 30, 2025 | Jun 12, 2025 | Administrative |
Zoning review Planning · CP-ZOC | May 27, 2025 | Jun 10, 2025 | Approved |
Building plan review Building Inspection · BLDG | May 27, 2025 | May 29, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | May 27, 2025 | Jun 3, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 27, 2025 | Jun 10, 2025 | Approved |
Fire prevention review Fire Department · SFFD | May 27, 2025 | Jun 5, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | May 27, 2025 | May 29, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | May 27, 2025 | Jun 6, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 27, 2025 | May 28, 2025 | Approved |
Development fee collection Building Inspection · DFCU | Jun 11, 2025 | Jun 11, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jun 12, 2025 | Jun 26, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $240,443
| Name | Role | License on permit |
|---|---|---|
| Gregory K Iboshi Huang Ibosh Architecture | Architect | C27547 |
| Donald David Double D Engineering | Engineer | S3928 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025