401 Parker Av
San Francisco permit 202504214820 · Lone Mountain/USF
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Alter site to pa# 201807104172. new scope: unit#1: 2 bedrooms with en-suite bath. l/r, kitchen, ffice, laundry & storage. unit#2: 3 bedroom with en-suite bath, powder rm, l/d, family rm, kitchen & storage space. unit# 3: 1 bedrm with en-suite bath, common bath, l/r & kthntt. u4:1 bdrm w/en-ste bth
- Filed
- May 13, 2025
- Issued
- Sep 8, 2026 (16 months after filing)
- Completed
- Not completed yet
- Review stops
- 39 stops across 6 departments
- Comments issued
- 6 times, by Planning, Building Inspection, Fire Department, Permit Center
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 11, 2025 | May 14, 2025 | Administrative |
Permit Center Permit Center · PERMIT-CTR | Apr 16, 2025 | May 7, 2025 | Approved |
Zoning review Planning · CP-ZOC | May 14, 2025 | May 27, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | May 14, 2025 | Jun 12, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | May 14, 2025 | Jun 10, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | May 14, 2025 | May 16, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | May 14, 2025 | May 16, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | May 14, 2025 | Jul 9, 2025 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | May 14, 2025 | May 14, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | May 14, 2025 | Aug 14, 2026 | Administrative |
Building plan review quality control Building Inspection · BLDG-QC | Jun 12, 2025 | Jun 12, 2025 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Oct 14, 2025 | Jul 24, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Dec 26, 2025 | Feb 18, 2026 | Approved |
Building plan review Building Inspection · BLDG | Dec 26, 2025 | Jan 12, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Dec 26, 2025 | Dec 31, 2025 | Not Applicable |
Fire prevention review Fire Department · SFFD | Dec 26, 2025 | Jan 13, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Dec 26, 2025 | Dec 30, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Dec 26, 2025 | Jan 11, 2026 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Dec 26, 2025 | Dec 26, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 4, 2026 | Feb 4, 2026 | Approved |
Building plan review Building Inspection · BLDG | Feb 24, 2026 | Feb 27, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Feb 27, 2026 | Feb 27, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 27, 2026 | Jul 29, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Jul 27, 2026 | Aug 14, 2026 | Approved-Stipulated |
Development fee collection Building Inspection · DFCU | Jul 27, 2026 | Aug 14, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | Aug 14, 2026 | Sep 8, 2026 | Administrative |
Addendum 1: Final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Sep 11, 2026 | Sep 25, 2026 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Oct 20, 2026 | Oct 30, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 2, 2026 | Nov 3, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Nov 3, 2026 | In progress | — |
Building plan review Building Inspection · BLDG | Nov 3, 2026 | In progress | — |
Structural plan approval Building Inspection · PAD-STR | Nov 3, 2026 | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | Nov 3, 2026 | In progress | — |
Fire prevention review Fire Department · SFFD | Nov 3, 2026 | In progress | — |
Street use and mapping Public Works · DPW-BSM | Nov 3, 2026 | In progress | — |
Urban forestry Public Works · DPW-BUF | Nov 3, 2026 | In progress | — |
Public Utilities Commission review Public Utilities · SFPUC | Nov 3, 2026 | In progress | — |
Permit Processing Center Building Inspection · PPC | Nov 3, 2026 | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $119,507
| Name | Role | License on permit |
|---|---|---|
| E Andrew Faust Mw Design | Architect | C28181 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jul 2008