99 Rhode Island St
San Francisco permit 202504285348 · Mission Bay
Full building renovation and change ofuse from office to private school (k-12) and group e childcare (+36mos).(e) on-site parking convert to outdoor play yard for students. mandatory seismic upgrade.
- Filed
- May 14, 2025
- Issued
- Oct 10, 2025 (5 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 38 stops across 7 departments
- Comments issued
- 9 times, by Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Apr 24, 2025 | May 13, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | May 14, 2025 | May 14, 2025 | Administrative |
Zoning review Planning · CP-ZOC | May 14, 2025 | May 15, 2025 | Approved |
Building plan review Building Inspection · BLDG | May 14, 2025 | Jun 16, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | May 14, 2025 | Aug 19, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | May 14, 2025 | May 18, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | May 14, 2025 | Jun 5, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | May 14, 2025 | May 16, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | May 14, 2025 | May 16, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | May 14, 2025 | Jul 14, 2025 | Not Applicable |
Public Utilities Commission review Public Utilities · SFPUC | May 14, 2025 | May 20, 2025 | Approved |
Public Health HEALTH-MH | May 14, 2025 | May 14, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | May 14, 2025 | Oct 10, 2025 | Administrative |
Zoning review Planning · CP-ZOC | May 15, 2025 | May 15, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jun 11, 2025 | Jun 11, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Jul 25, 2025 | Aug 4, 2025 | In Progress |
Mechanical and energy plan review Building Inspection · MECH | Jul 25, 2025 | Jul 28, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jul 28, 2025 | Jul 28, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Aug 6, 2025 | Aug 6, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 17, 2025 | Sep 19, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Sep 18, 2025 | Sep 18, 2025 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Sep 22, 2025 | Sep 25, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Sep 24, 2025 | Sep 29, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Sep 26, 2025 | Sep 26, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 26, 2025 | Sep 26, 2025 | Approved |
Zoning review Planning · CP-ZOC | Sep 30, 2025 | Sep 30, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 30, 2025 | Oct 3, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Oct 1, 2025 | Oct 1, 2025 | Approved-Stipulated |
Building plan review Building Inspection · BLDG | Oct 2, 2025 | Oct 2, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Oct 2, 2025 | Oct 2, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 3, 2025 | Oct 7, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Oct 7, 2025 | Oct 7, 2025 | Administrative |
Electrical plan review Building Inspection · MECH-E | Oct 7, 2025 | Oct 7, 2025 | Approved |
Zoning review Planning · CP-ZOC | Oct 8, 2025 | Oct 9, 2025 | Approved |
Building plan review Building Inspection · BLDG | Oct 8, 2025 | Oct 8, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Oct 8, 2025 | Oct 8, 2025 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Oct 9, 2025 | Oct 9, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 10, 2025 | Oct 10, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $15,000,000
| Name | Role | License on permit |
|---|---|---|
| Joshua Sawyer Cohn C A Architects | Architect | C23410 |
| Chris Warner Zfa Structural Enginers | Engineer | S-4613 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2024