55 Ashbury Tr
San Francisco permit 202504285365 · Haight Ashbury
OtherOver-the-counter, with plansFiled
Scope of work
As written on the permit application.
(n) electric chair lift to be installed at entry stair to provide accessible path to entrance door. no interior work.
Timeline
Key dates from the city record.
- Filed
- Apr 28, 2025
- Issued
- Not issued yet
- Completed
- Not completed yet
City plan review
Each review stop the plans went through, from the city's routing record.
- Review stops
- 5 stops across 2 departments
- Comments issued
- Once, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Apr 28, 2025 | Apr 28, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Apr 28, 2025 | Apr 28, 2025 | Approved |
Building plan review Building Inspection · BLDG | Apr 28, 2025 | Apr 28, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | May 5, 2025 | May 5, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
Permit details
- Permit type
- OTC alterations permit
- Status
- Filed
- Estimated cost
- $3,000
People named on this permit
Only people we matched to a California license are listed.
| Name | Role | License on permit |
|---|---|---|
| Parvathy Nair | Architect | C38498 |
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202504285365 on the city's permit tracking site
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2025