2430 Leavenworth St
San Francisco permit 202504295411 · Russian Hill
Retaining wall stabilization on property line with 2420 leavenworth street includes tiebacks & deadman piers.
- Filed
- May 12, 2025
- Issued
- Aug 21, 2025 (3 months after filing)
- Completed
- Dec 23, 2025 (4 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 11 stops across 4 departments
- Comments issued
- None
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Apr 21, 2025 | May 9, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 29, 2025 | May 12, 2025 | Administrative |
Zoning review Planning · CP-ZOC | May 12, 2025 | Aug 18, 2025 | Approved |
Building plan review Building Inspection · BLDG | May 12, 2025 | Jun 26, 2025 | Administrative |
Structural plan approval Building Inspection · PAD-STR | May 12, 2025 | Jun 26, 2025 | Administrative |
Fire prevention review Fire Department · SFFD | May 12, 2025 | May 22, 2025 | Not Applicable |
Permit Processing Center Building Inspection · PPC | May 12, 2025 | Aug 18, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Jun 26, 2025 | Jun 26, 2025 | Not Applicable |
Building plan review Building Inspection · BLDG | Jul 24, 2025 | Jul 31, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jul 24, 2025 | Jul 31, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 18, 2025 | Aug 21, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $67,492
| Name | Role | License on permit |
|---|---|---|
| Christopher Lane Wilhite Engineered Soil Repairs | Engineer | C63465 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2022