639 04th Av
San Francisco permit 202505015597 · Inner Richmond
Interior renovation of all floors, connect level 1 with garage level with new internal stair to add 446 sf of habitable space. level 2 and level 3: add 13 sf of area at rear wall by straighten rear walls. change extent and configuration of deck at rear.
- Filed
- Jun 7, 2025
- Issued
- Nov 17, 2025 (5 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 19 stops across 5 departments
- Comments issued
- 6 times, by Permit Center, Building Inspection, Fire Department, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Apr 30, 2025 | May 13, 2025 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | May 26, 2025 | Jun 4, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 6, 2025 | Jun 9, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jun 9, 2025 | Jun 17, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jun 9, 2025 | Jul 29, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jun 9, 2025 | Jul 25, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Jun 9, 2025 | Jul 15, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 9, 2025 | Jun 12, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jun 9, 2025 | Jun 17, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Jun 9, 2025 | Oct 30, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Sep 17, 2025 | Oct 20, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 17, 2025 | Sep 30, 2025 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Sep 18, 2025 | Sep 18, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Sep 23, 2025 | Sep 23, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 20, 2025 | Oct 20, 2025 | Approved |
Zoning review Planning · CP-ZOC | Oct 22, 2025 | Oct 30, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Oct 22, 2025 | Oct 29, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 22, 2025 | Oct 23, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 30, 2025 | Nov 17, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $839,317
| Name | Role | License on permit |
|---|---|---|
| Winnie W Chen Winnie W Chen | Architect | C-36993 |
| Horon Lee Horon Lee | Engineer | S3818 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025