1270 A South Van Ness Av #0
San Francisco permit 202505025683 · Mission
Roof deck rebuild over (e) bedroom. replcae walls in (e) bedrooms w/ new 2x4 sheetrock/insulation after demo to hold the deck. new joist & flooring in (e) bedroom.
- Filed
- Jul 1, 2025
- Issued
- Sep 23, 2025 (3 months after filing)
- Completed
- Aug 27, 2026 (11 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 14 stops across 3 departments
- Comments issued
- 3 times, by Permit Center, Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | May 1, 2025 | May 20, 2025 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Jun 18, 2025 | Jun 30, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 30, 2025 | Jul 1, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jul 1, 2025 | Aug 6, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jul 1, 2025 | Aug 20, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jul 1, 2025 | Aug 20, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 1, 2025 | Jul 22, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Jul 1, 2025 | Sep 16, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Aug 5, 2025 | Aug 6, 2025 | Approved |
Zoning review Planning · CP-ZOC | Sep 2, 2025 | Sep 16, 2025 | Approved |
Building plan review Building Inspection · BLDG | Sep 2, 2025 | Sep 4, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Sep 2, 2025 | Sep 4, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 2, 2025 | Sep 9, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 16, 2025 | Sep 23, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $60,000
| Name | Role | License on permit |
|---|---|---|
| Venkata Rohit Grandhi Venkata Roht Grandhi | Engineer | C-88709 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2025