CheckMyDesigner

3969 Washington St

San Francisco permit 202505055754 · Presidio Heights

AdditionFull plan reviewIssued
Street view · Jan 2025
Google Street View of 3969 Washington St, Jan 2025
Scope of work
As written on the permit application.

Demo 1-story rear addition at rear, 8'x8' roof dormer window, rear yard deck, retain (e) deck firewall. in-fill @ west side blind wall (a0.6 neighbor consent ltr). new rear windows & siding; demo interior partitions & fixtures, remodel interior areas, electrical, plumbing & hvac work; foundation

Timeline
Key dates from the city record.
Filed
May 16, 2025
Issued
Sep 26, 2025 (4 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
24 stops across 6 departments
Comments issued
6 times, by Building Inspection, Public Works
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

May 16, 2025Approved

Central Permit Bureau

Building Inspection · CPB

May 19, 2025Administrative

Zoning review

Planning · CP-ZOC

May 27, 2025Approved

Building plan review

Building Inspection · BLDG

Jul 14, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Jul 14, 2025Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jul 16, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

May 20, 2025Approved-Stipulated

Street use and mapping

Public Works · DPW-BSM

May 21, 2025Issued Comments

Urban forestry

Public Works · DPW-BUF

Jul 15, 2025Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

May 27, 2025Approved

Permit Processing Center

Building Inspection · PPC

Sep 17, 2025Administrative

Building plan review

Building Inspection · BLDG

Aug 21, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Aug 20, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Aug 14, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Aug 19, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Aug 28, 2025Approved

Zoning review

Planning · CP-ZOC

Sep 4, 2025Approved

Building plan review

Building Inspection · BLDG

Sep 4, 2025Approved

Structural plan approval

Building Inspection · PAD-STR

Sep 3, 2025Approved

Fire prevention review

Fire Department · SFFD

Sep 2, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Sep 3, 2025Approved

Urban forestry

Public Works · DPW-BUF

Aug 29, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Sep 8, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Sep 26, 2025Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$1,500,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Alan Bryan Fox

Five Design

ArchitectC-36311
Lawrence Tik Man Wong

L Wong Engineering

Engineer5135
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202505055754 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record