14 Retiro Wy
San Francisco permit 202505075960 · Marina
Unit 14( on 2nd floor) - remodel bathroom, kitchen, laundry. electrical and plumbing update. new fireplace gas line, move kitchen gas line. increase power from 200 to 400 amp. no exterior work.
- Filed
- May 7, 2025
- Issued
- May 7, 2025 (within 1 month of filing)
- Completed
- Feb 3, 2026 (9 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2025 were typically issued within 1 month (median of 5,178 issued permits).
- Review stops
- 6 stops across 3 departments
- Comments issued
- None
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | May 7, 2025 | May 7, 2025 | Administrative |
Building plan review Building Inspection · BLDG | May 7, 2025 | May 7, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 7, 2025 | May 7, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | May 7, 2025 | May 7, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 7, 2025 | May 7, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | May 7, 2025 | May 7, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $140,000
| Name | Role | License on permit |
|---|---|---|
| Ketki C Shah Muffeny Shah Architects | Architect | C28460 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025