190 Saint Germain Av #0
San Francisco permit 202505096154 · Twin Peaks
Demo 3rd floor deck and replace 3rd floor sliding doors with windows. remodel existing closet.
- Filed
- May 9, 2025
- Issued
- Oct 8, 2025 (5 months after filing)
- Completed
- Feb 5, 2026 (4 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2025 were typically issued within 1 month (median of 5,178 issued permits).
- Review stops
- 7 stops across 2 departments
- Comments issued
- None
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | May 9, 2025 | May 9, 2025 | Administrative |
Zoning review Planning · CP-ZOC | May 9, 2025 | May 9, 2025 | Approved |
Building plan review Building Inspection · BLDG | May 9, 2025 | May 9, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | May 9, 2025 | May 9, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 9, 2025 | May 9, 2025 | Approved |
Building plan review Building Inspection · BLDG | Oct 8, 2025 | Oct 8, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Oct 8, 2025 | Oct 8, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $25,000
| Name | Role | License on permit |
|---|---|---|
| Geoffrey S Gainer Actual-Size Architecture | Architect | C27762 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2019