86 Sussex St
San Francisco permit 202505096162 · Glen Park
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Reduction in scope to issued bpa# 2022-1027-5297; fire sprinklers are not required and will not be provided for this project.
- Filed
- May 29, 2025
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 21 stops across 4 departments
- Comments issued
- 3 times, by Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | May 6, 2025 | May 15, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | May 16, 2025 | May 29, 2025 | Administrative |
Building plan review Building Inspection · BLDG | May 29, 2025 | Jul 22, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | May 29, 2025 | Jun 6, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | May 29, 2025 | May 30, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | May 29, 2025 | Jul 15, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | May 29, 2025 | In progress | In Progress |
Building plan review quality control Building Inspection · BLDG-QC | Jul 21, 2025 | Jul 22, 2025 | Approved |
Building plan review Building Inspection · BLDG | Aug 22, 2025 | Aug 27, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Aug 22, 2025 | Oct 14, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Aug 22, 2025 | Aug 25, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 22, 2025 | Aug 27, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Aug 22, 2025 | Sep 18, 2025 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Sep 5, 2025 | Sep 5, 2025 | Approved |
Building plan review Building Inspection · BLDG | Sep 8, 2025 | Sep 8, 2025 | Approved |
Development fee collection Building Inspection · DFCU | Sep 18, 2025 | Sep 19, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Oct 10, 2025 | Oct 15, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Oct 10, 2025 | Oct 20, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 10, 2025 | Oct 14, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Oct 10, 2025 | Oct 20, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $1
| Name | Role | License on permit |
|---|---|---|
| Ernest Hartley Selander Selander Architects | Architect | C12715 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2022