451 Pacific Av
San Francisco permit 202505126265 · Chinatown
Addition of new enclosed exit stair extending from level b to 2;(n) elevator erviing lvl 1,1m,2,2m,3.construction & assoc demo for the partial reframing of mezz.mod to steel bracing frams and seismic bracing.(n) partitions,elevator shaft, exit stair.new ada baths, lighting & finishes.
- Filed
- Jun 6, 2025
- Issued
- Nov 21, 2025 (6 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 18 stops across 4 departments
- Comments issued
- 6 times, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | May 8, 2025 | May 23, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 6, 2025 | Jun 6, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Jun 6, 2025 | Jul 28, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jun 6, 2025 | Jul 27, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 6, 2025 | Jul 17, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 6, 2025 | Jun 9, 2025 | Not Applicable |
Permit Processing Center Building Inspection · PPC | Jun 6, 2025 | Nov 17, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Sep 2, 2025 | Sep 11, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 2, 2025 | Sep 2, 2025 | Approved-Stipulated |
Structural plan approval Building Inspection · PAD-STR | Sep 5, 2025 | Sep 8, 2025 | Issued Comments |
Building plan review quality control Building Inspection · BLDG-QC | Sep 10, 2025 | Sep 11, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Sep 17, 2025 | Sep 19, 2025 | Approved |
Building plan review Building Inspection · BLDG | Sep 23, 2025 | Oct 8, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Nov 3, 2025 | Nov 3, 2025 | Not Applicable |
Building plan review Building Inspection · BLDG | Nov 11, 2025 | Nov 13, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Nov 12, 2025 | Nov 12, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Nov 14, 2025 | Nov 17, 2025 | Approved-Stipulated |
Central Permit Bureau Building Inspection · CPB | Nov 17, 2025 | Nov 21, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $2,100,000
| Name | Role | License on permit |
|---|---|---|
| Michael Joseph Castro Brereton Architects | Architect | C-24073 |
| Alan Charles Burr Murphy Burr Curry | Engineer | S5062 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026