2625 San Jose Av
San Francisco permit 202505136338 · Oceanview/Merced/Ingleside
Convert garage to new adu per planning code sec.207.2 (state adu) to add unit# 5. add new kitchen.
- Filed
- May 23, 2025
- Issued
- Feb 13, 2026 (9 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 22 stops across 6 departments
- Comments issued
- 9 times, by Planning, Building Inspection, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | May 5, 2025 | May 19, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | May 13, 2025 | May 27, 2025 | Administrative |
Zoning review Planning · CP-ZOC | May 27, 2025 | Jun 13, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | May 27, 2025 | May 30, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 27, 2025 | Jun 4, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | May 27, 2025 | Jun 6, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | May 27, 2025 | May 29, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | May 27, 2025 | May 27, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | May 27, 2025 | May 29, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | May 27, 2025 | Nov 13, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Jun 4, 2025 | Jun 4, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Oct 28, 2025 | Nov 5, 2025 | Approved |
Building plan review Building Inspection · BLDG | Oct 28, 2025 | Nov 6, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 28, 2025 | Nov 4, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 28, 2025 | Nov 12, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 28, 2025 | Oct 29, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Oct 28, 2025 | Nov 12, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Oct 28, 2025 | Oct 29, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 12, 2025 | Nov 12, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Nov 13, 2025 | Nov 13, 2025 | Approved |
Development fee collection Building Inspection · DFCU | Nov 13, 2025 | Nov 13, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Nov 13, 2025 | Feb 13, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $122,636
| Name | Role | License on permit |
|---|---|---|
| L A Paul L.A. Paul & Associates | Architect | C8725 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025