CheckMyDesigner

1051 Geneva Av

San Francisco permit 202505136353 · Excelsior

ADUFull plan reviewComplete
Street view · Aug 2022
Google Street View of 1051 Geneva Av, Aug 2022
Scope of work
As written on the permit application.

Convert (e) home office on 1/f into adu per pc s207.2. add new stove to (e) kitchenette; add new enclosed open space for the adu; provide sep heating and electrical to the adu.

Timeline
Key dates from the city record.
Filed
Aug 14, 2025
Issued
Nov 12, 2025 (3 months after filing)
Completed
Feb 27, 2026 (4 months after issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
30 stops across 6 departments
Comments issued
3 times, by Permit Center, Building Inspection
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

May 19, 2025Issued Comments

Permit Center

Permit Center · PERMIT-CTR

Jul 24, 2025Issued Comments

Permit Center

Permit Center · PERMIT-CTR

Aug 12, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Aug 14, 2025Administrative

Zoning review

Planning · CP-ZOC

Aug 20, 2025Approved

Building plan review

Building Inspection · BLDG

Aug 19, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Aug 19, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

Aug 25, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Aug 18, 2025Approved

Urban forestry

Public Works · DPW-BUF

Sep 29, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Aug 19, 2025Approved

Building inspector

Building Inspection · BID-INSP

Sep 22, 2025Approved

Permit Processing Center

Building Inspection · PPC

Oct 16, 2025Administrative

Zoning review

Planning · CP-ZOC

Aug 20, 2025Administrative

Zoning review

Planning · CP-ZOC

Sep 11, 2025Approved

Building plan review

Building Inspection · BLDG

Sep 11, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Sep 26, 2025Approved

Fire prevention review

Fire Department · SFFD

Sep 11, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Sep 11, 2025Approved

Urban forestry

Public Works · DPW-BUF

Oct 1, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Sep 12, 2025Approved

Development fee collection

Building Inspection · DFCU

Oct 1, 2025Administrative

Zoning review

Planning · CP-ZOC

Oct 8, 2025Approved

Building plan review

Building Inspection · BLDG

Oct 3, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Oct 6, 2025Approved

Fire prevention review

Fire Department · SFFD

Oct 6, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Oct 6, 2025Approved

Urban forestry

Public Works · DPW-BUF

Oct 8, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Oct 15, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Nov 12, 2025Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$36,657
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Patrick Ivan Mora

Mora Architects

ArchitectC15322
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202505136353 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record