67 Potomac St
San Francisco permit 202505156539 · Haight Ashbury
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Revision to pa# 202205103946. new elevator at all 4 floors & changes to interior layout to accomodate new elevator, building footprint is the same as previously permitted drawings. revised structural design & calculations.
- Filed
- May 21, 2025
- Issued
- Sep 11, 2025 (4 months after filing)
- Completed
- Not completed yet
- Review stops
- 18 stops across 6 departments
- Comments issued
- 3 times, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | May 6, 2025 | May 21, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | May 15, 2025 | May 21, 2025 | Administrative |
Zoning review Planning · CP-ZOC | May 21, 2025 | Jul 9, 2025 | Not Applicable |
Building plan review Building Inspection · BLDG | May 21, 2025 | Jul 11, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | May 21, 2025 | Jul 11, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 21, 2025 | Jul 7, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | May 21, 2025 | Jun 25, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | May 21, 2025 | May 27, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 21, 2025 | Jun 3, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | May 21, 2025 | Sep 2, 2025 | Administrative |
Building plan review quality control Building Inspection · BLDG-QC | Jul 11, 2025 | Jul 11, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Aug 4, 2025 | Aug 11, 2025 | Approved |
Building plan review Building Inspection · BLDG | Aug 5, 2025 | Aug 14, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Aug 5, 2025 | Aug 5, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Aug 15, 2025 | Aug 25, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 15, 2025 | Aug 21, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 15, 2025 | Aug 26, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 2, 2025 | Sep 11, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $100,000
| Name | Role | License on permit |
|---|---|---|
| Brooks Mitchell Mcdonald Brooks Mcdonald Architecture | Architect | C33087 |
| David M Strandberg Strandberg Engineering | Engineer | 62993 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Aug 2015