1/f: (n) 795sf adu. convert (e) garage into (n) bedroom, convert (e) media room into (n) kitchen & (e) bedroom into (n) living room.
- Filed
- Jul 7, 2025
- Issued
- Dec 17, 2025 (5 months after filing)
- Completed
- Aug 3, 2026 (8 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 27 stops across 6 departments
- Comments issued
- 5 times, by Permit Center, Planning, Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | May 14, 2025 | May 23, 2025 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Jun 24, 2025 | Jul 7, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 8, 2025 | Jul 8, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jul 8, 2025 | Jul 10, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Jul 8, 2025 | Jul 10, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 8, 2025 | Jul 15, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jul 8, 2025 | Jul 15, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 8, 2025 | Jul 10, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Jul 8, 2025 | Jul 9, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 8, 2025 | Jul 22, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Jul 8, 2025 | Sep 29, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Aug 22, 2025 | Sep 5, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Aug 22, 2025 | Sep 2, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 22, 2025 | Sep 2, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Aug 22, 2025 | Aug 26, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 22, 2025 | Aug 25, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Aug 22, 2025 | Sep 3, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 22, 2025 | Aug 29, 2025 | Approved |
Zoning review Planning · CP-ZOC | Sep 11, 2025 | Sep 18, 2025 | Approved |
Building plan review Building Inspection · BLDG | Sep 11, 2025 | Sep 16, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 11, 2025 | Sep 26, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Sep 11, 2025 | Sep 16, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 11, 2025 | Sep 15, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Sep 11, 2025 | Sep 26, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 11, 2025 | Sep 12, 2025 | Approved |
Development fee collection Building Inspection · DFCU | Sep 26, 2025 | Sep 26, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Sep 29, 2025 | Dec 17, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $89,217
| Name | Role | License on permit |
|---|---|---|
| Thao Do Hc Design & Management | Architect | C-38594 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2023