Commercial tenant improvement for future grocery store.

Timeline
Key dates from the city record.
Filed
Jun 18, 2025
Issued
Dec 26, 2025 (6 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
51 stops across 4 departments
Comments issued
12 times, by Building Inspection, Public Health
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Jun 2, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Jun 6, 2025Administrative

Building plan review

Building Inspection · BLDG

Jun 27, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Jul 8, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Jun 26, 2025Issued Comments

Electrical plan review

Building Inspection · MECH-E

Jun 20, 2025Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Jun 27, 2025Approved

Public Utilities programs review

Public Utilities · SFPUC-PRG

Jun 25, 2025Approved-Stipulated

Public health food review

Public Health · HEALTH-FD

Jun 6, 2025Issued Comments

Permit Processing Center

Building Inspection · PPC

Oct 30, 2025Administrative

Public Health

HEALTH-HM

Jun 9, 2025Approved

Public health food review

Public Health · HEALTH-FD

Jun 23, 2025Issued Comments

Mechanical plan review quality control

Building Inspection · MECH-QC

Jun 27, 2025Approved

Plumbing plan check

Building Inspection · PID-PC

Aug 20, 2025Approved-Stipulated

Building plan review

Building Inspection · BLDG

Aug 13, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Aug 14, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Aug 4, 2025Approved

Electrical plan review

Building Inspection · MECH-E

Aug 12, 2025Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Aug 8, 2025Approved

Public Utilities programs review

Public Utilities · SFPUC-PRG

Aug 4, 2025Approved-Stipulated

Public health food review

Public Health · HEALTH-FD

Aug 5, 2025Issued Comments

Public Health

HEALTH-HM

Aug 4, 2025Approved

Building plan review

Building Inspection · BLDG

Aug 15, 2025Issued Comments

Building plan review

Building Inspection · BLDG

Sep 18, 2025Approved

Structural plan approval

Building Inspection · PAD-STR

Sep 16, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Sep 16, 2025Approved

Electrical plan review

Building Inspection · MECH-E

Sep 19, 2025Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Sep 10, 2025Approved

Public Utilities programs review

Public Utilities · SFPUC-PRG

Sep 25, 2025Approved

Public health food review

Public Health · HEALTH-FD

Sep 22, 2025Issued Comments

Public Health

HEALTH-HM

Sep 10, 2025Approved

Plumbing plan check

Building Inspection · PID-PC

Oct 8, 2025Approved

Building plan review

Building Inspection · BLDG

Oct 20, 2025Approved

Structural plan approval

Building Inspection · PAD-STR

Oct 9, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Oct 7, 2025Approved

Electrical plan review

Building Inspection · MECH-E

Oct 8, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Oct 6, 2025Approved

Public Utilities programs review

Public Utilities · SFPUC-PRG

Oct 14, 2025Approved

Public health food review

Public Health · HEALTH-FD

Oct 6, 2025Issued Comments

Public Health

HEALTH-HM

Oct 2, 2025Approved

Building plan review

Building Inspection · BLDG

Oct 23, 2025Approved

Structural plan approval

Building Inspection · PAD-STR

Oct 27, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Oct 21, 2025Administrative

Electrical plan review

Building Inspection · MECH-E

Oct 21, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Oct 22, 2025Approved

Public Utilities programs review

Public Utilities · SFPUC-PRG

Oct 24, 2025Approved

Public health food review

Public Health · HEALTH-FD

Oct 22, 2025Approved

Public Health

HEALTH-HM

Oct 21, 2025Approved

Plumbing plan check

Building Inspection · PID-PC

Oct 27, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Oct 30, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Dec 26, 2025Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$15,000,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Kevin Gerald Morton

Honbach-Lewin Inc

Engineer5181
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202505196735 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record