611 San Jose Av
San Francisco permit 202505216953 · Bernal Heights
Conversion of basement/ll into adu, includes addition of sq ft in rear. modify (e) half bath & closet on 2/l for full bath & remove (e) stairs from basement to main level. convert (e) deck to sunroom & add (n) deck w/ stair to rear yard.
- Filed
- Jun 2, 2025
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 57 stops across 6 departments
- Comments issued
- 16 times, by Planning, Building Inspection, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | May 19, 2025 | May 29, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | May 30, 2025 | Jun 3, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jun 3, 2025 | Jun 3, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Jun 3, 2025 | Jul 9, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jun 3, 2025 | Jul 9, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 3, 2025 | Jun 19, 2025 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Jun 3, 2025 | Jun 4, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jun 3, 2025 | Jun 4, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Jun 3, 2025 | Jul 2, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jun 3, 2025 | Jun 5, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Jun 3, 2025 | In progress | Administrative |
Zoning review Planning · CP-ZOC | Aug 21, 2025 | Sep 30, 2025 | Approved |
Building plan review Building Inspection · BLDG | Aug 21, 2025 | Sep 5, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Aug 21, 2025 | Sep 5, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 21, 2025 | Sep 2, 2025 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Aug 21, 2025 | Aug 25, 2025 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Aug 21, 2025 | Aug 22, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Aug 21, 2025 | Sep 2, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 21, 2025 | Aug 25, 2025 | Approved |
Building plan review Building Inspection · BLDG | Sep 10, 2025 | Sep 15, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Sep 10, 2025 | Sep 15, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 10, 2025 | Sep 22, 2025 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Sep 10, 2025 | Sep 11, 2025 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Sep 10, 2025 | Sep 12, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Sep 10, 2025 | Sep 26, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 10, 2025 | Sep 12, 2025 | Approved |
Zoning review Planning · CP-ZOC | Dec 1, 2025 | Dec 1, 2025 | Administrative |
Development fee collection Building Inspection · DFCU | Dec 1, 2025 | Dec 1, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Dec 11, 2025 | Dec 16, 2025 | Approved |
Building plan review Building Inspection · BLDG | Dec 11, 2025 | Dec 15, 2025 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Dec 11, 2025 | Dec 15, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Dec 11, 2025 | Dec 30, 2025 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Dec 11, 2025 | Dec 17, 2025 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Dec 11, 2025 | Dec 12, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Dec 11, 2025 | Dec 19, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 11, 2025 | Dec 12, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 30, 2025 | In progress | In Progress |
Zoning review Planning · CP-ZOC | Jul 1, 2026 | Jul 2, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Jul 1, 2026 | Jul 17, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jul 1, 2026 | Jul 17, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 1, 2026 | Jul 6, 2026 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Jul 1, 2026 | Jul 2, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Jul 1, 2026 | Jul 8, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Jul 1, 2026 | Jul 28, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 1, 2026 | Jul 7, 2026 | Approved |
Zoning review Planning · CP-ZOC | Aug 31, 2026 | Sep 2, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Aug 31, 2026 | Sep 11, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Aug 31, 2026 | Sep 11, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 31, 2026 | Sep 3, 2026 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Aug 31, 2026 | Sep 3, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Aug 31, 2026 | Sep 2, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Aug 31, 2026 | Sep 24, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 31, 2026 | Sep 4, 2026 | Approved |
Zoning review Planning · CP-ZOC | Oct 23, 2026 | Oct 23, 2026 | Issued Comments |
Zoning review Planning · CP-ZOC | — | In progress | — |
Building plan review Building Inspection · BLDG | — | In progress | — |
Structural plan approval Building Inspection · PAD-STR | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Approved
- Estimated cost
- $300,000
| Name | Role | License on permit |
|---|---|---|
| Charles Shelton Jr Green As Architecture, Inc | Architect | C37167 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2024