706 Sansome St #0
San Francisco permit 202505216975 · Chinatown
Basement & 1st/f: interior t.i. demo of non structural interior partitions, doors, ceiling finishes, mep. new partitions, doors, finihes, ceiling, mep. work also included ada restrooms upgrdes
- Filed
- May 21, 2025
- Issued
- Mar 3, 2026 (9 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2025 were typically issued within 1 month (median of 5,178 issued permits).
- Review stops
- 13 stops across 3 departments
- Comments issued
- 6 times, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | May 21, 2025 | May 21, 2025 | Administrative |
Zoning review Planning · CP-ZOC | May 21, 2025 | May 21, 2025 | Not Applicable |
Building plan review Building Inspection · BLDG | May 21, 2025 | May 21, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 23, 2025 | May 23, 2025 | Approved-Stipulated |
Building plan review Building Inspection · BLDG | May 29, 2025 | May 29, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Jun 3, 2025 | Jun 3, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Jun 11, 2025 | Jun 11, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Jun 12, 2025 | Jun 12, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Jun 13, 2025 | Jun 13, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Jun 16, 2025 | Jun 16, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 18, 2025 | Jun 18, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 18, 2025 | Jun 18, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 3, 2026 | Mar 3, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Issued
- Estimated cost
- $629,748
| Name | Role | License on permit |
|---|---|---|
| Wesley Alan Herr | Architect | C40025 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026