116 Merced Av
San Francisco permit 202505287349 · West of Twin Peaks
Rooms down permit - to comply with nov 201973412 (dbi) and nov 2019016589 (enf planning). removal at illegal dwelling unit with removal of stove. legalizw unpermitted habitable space on ground floor level
- Filed
- Jun 16, 2025
- Issued
- Mar 10, 2026 (9 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 19 stops across 5 departments
- Comments issued
- 4 times, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | May 26, 2025 | Jun 9, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 13, 2025 | Jun 16, 2025 | Administrative |
Permit Processing Center Building Inspection · PPC | Jun 16, 2025 | Mar 3, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jun 17, 2025 | Aug 6, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jun 17, 2025 | Aug 6, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 17, 2025 | Jul 22, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 17, 2025 | Jun 18, 2025 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Jun 17, 2025 | Jul 3, 2025 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Aug 6, 2025 | Aug 6, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jan 16, 2026 | Feb 25, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 16, 2026 | Jan 22, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 16, 2026 | Jan 21, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 16, 2026 | Jan 23, 2026 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Jan 16, 2026 | Jan 20, 2026 | Approved |
Building plan review Building Inspection · BLDG | Feb 19, 2026 | Mar 3, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 19, 2026 | Feb 23, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Feb 19, 2026 | Feb 20, 2026 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Feb 19, 2026 | Feb 20, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 3, 2026 | Mar 10, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $351,813
| Name | Role | License on permit |
|---|---|---|
| Janet Coral Campbell Campbell & Associates | Architect | C18808 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2022