649 Fillmore St
San Francisco permit 202505287351 · Hayes Valley
Floor '4': convert attic to habitable area to unit 649. add interior connecting stair. create bedroom, (2) baths, family room and utility. create dormers utilizing za bulletin no. 3
- Filed
- Jul 30, 2025
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 18 stops across 6 departments
- Comments issued
- 6 times, by Building Inspection, Fire Department, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | May 27, 2025 | Jun 9, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 30, 2025 | Jul 30, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jul 31, 2025 | Aug 4, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jul 31, 2025 | Sep 5, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jul 31, 2025 | Sep 5, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Jul 31, 2025 | Aug 28, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jul 31, 2025 | Oct 9, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jul 31, 2025 | Aug 7, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Jul 31, 2025 | Aug 11, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 31, 2025 | Aug 6, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Jul 31, 2025 | In progress | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 17, 2026 | Mar 26, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 23, 2026 | Mar 23, 2026 | Approved |
Building plan review Building Inspection · BLDG | Mar 31, 2026 | Mar 31, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Jun 2, 2026 | Jun 5, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | — | In progress | — |
Fire prevention review Fire Department · SFFD | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $200,000
| Name | Role | License on permit |
|---|---|---|
| Curtis Jude Hollenbeck Curtis Hollenbeck Architect | Architect | C24843 |
| Engin Yagmur Ecr Engineering | Engineer | C-76016 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026