12 Chattanooga St
San Francisco permit 202505287391 · Noe Valley
#b: 1)create a 61 ft closet for the master bedroom. 2)remove an existing and install a new window to the dining room. 3)install a new window in the closet. 4)install a skylight in the bathroom. 5)install new 2-zone mini-split
- Filed
- Jun 19, 2025
- Issued
- Feb 3, 2026 (8 months after filing)
- Completed
- Jul 13, 2026 (5 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 22 stops across 4 departments
- Comments issued
- 6 times, by Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | May 28, 2025 | May 28, 2025 | Administrative |
Zoning review Planning · CP-ZOC | May 28, 2025 | May 28, 2025 | Approved |
Permit Center Permit Center · PERMIT-CTR | May 30, 2025 | Jun 13, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 20, 2025 | Jun 20, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jun 20, 2025 | Jun 23, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jun 20, 2025 | Aug 5, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jun 20, 2025 | Aug 4, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 20, 2025 | Jul 24, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 20, 2025 | Jun 23, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Jun 20, 2025 | Jan 26, 2026 | Administrative |
Fire prevention review Fire Department · SFFD | Oct 23, 2025 | Oct 23, 2025 | Approved-Stipulated |
Mechanical and energy plan review Building Inspection · MECH | Oct 24, 2025 | Oct 28, 2025 | Approved |
Building plan review Building Inspection · BLDG | Oct 28, 2025 | Oct 28, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Oct 29, 2025 | Oct 29, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Nov 13, 2025 | Nov 13, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 5, 2025 | Dec 5, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jan 9, 2026 | Jan 9, 2026 | Approved |
Zoning review Planning · CP-ZOC | Jan 14, 2026 | Jan 20, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jan 14, 2026 | Jan 14, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 14, 2026 | Jan 20, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jan 14, 2026 | Jan 22, 2026 | Approved-Stipulated |
Central Permit Bureau Building Inspection · CPB | Jan 26, 2026 | Feb 3, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $88,915
| Name | Role | License on permit |
|---|---|---|
| Erik Mcgregor Wmstructural | Engineer | S6802 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026