805 A Garfield St
San Francisco permit 202505287393 · Oceanview/Merced/Ingleside
Legalize existing ground floor space and convert into adu, convert existing wet bar into new kitchen for adu use 667 sf, ground flr space completed under 200807116514.
- Filed
- Jul 8, 2025
- Issued
- Mar 19, 2026 (8 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 40 stops across 6 departments
- Comments issued
- 10 times, by Permit Center, Building Inspection, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | May 23, 2025 | Jun 10, 2025 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Jun 18, 2025 | Jul 3, 2025 | Approved |
Apartment and hotel inspection Building Inspection · HIS | Jun 24, 2025 | Jun 24, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 3, 2025 | Jul 9, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jul 9, 2025 | Jul 10, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jul 9, 2025 | Jul 15, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jul 9, 2025 | Jul 14, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 9, 2025 | Jul 15, 2025 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Jul 9, 2025 | Jul 15, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jul 9, 2025 | Jul 10, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Jul 9, 2025 | Jul 15, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jul 9, 2025 | Jul 22, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Jul 9, 2025 | Oct 21, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Aug 5, 2025 | Aug 8, 2025 | Approved |
Building plan review Building Inspection · BLDG | Aug 5, 2025 | Aug 7, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Aug 5, 2025 | Aug 12, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 5, 2025 | Aug 6, 2025 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Aug 5, 2025 | Aug 13, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 5, 2025 | Aug 6, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Aug 5, 2025 | Aug 7, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 5, 2025 | Aug 7, 2025 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Aug 20, 2025 | Aug 20, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Aug 25, 2025 | Sep 5, 2025 | Approved |
Building plan review Building Inspection · BLDG | Aug 25, 2025 | Sep 2, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Aug 25, 2025 | Sep 8, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 25, 2025 | Sep 3, 2025 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Aug 25, 2025 | Aug 26, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 25, 2025 | Aug 26, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Aug 25, 2025 | Aug 26, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 25, 2025 | Sep 2, 2025 | Approved |
Zoning review Planning · CP-ZOC | Sep 11, 2025 | Sep 18, 2025 | Approved |
Building plan review Building Inspection · BLDG | Sep 11, 2025 | Sep 16, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Sep 11, 2025 | Sep 23, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 11, 2025 | Sep 12, 2025 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Sep 11, 2025 | Sep 16, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 11, 2025 | Sep 15, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Sep 11, 2025 | Oct 6, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 11, 2025 | Sep 12, 2025 | Approved |
Development fee collection Building Inspection · DFCU | Oct 20, 2025 | Oct 20, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Oct 21, 2025 | Mar 19, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $22,382
| Name | Role | License on permit |
|---|---|---|
| Tuong Tran | Engineer | C56209 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2022