2950 Pacific Av
San Francisco permit 202505297471 · Pacific Heights
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Facade alt and addition of 2 basement levels to (e).windows replacement,addition of garage and landscaping elements.new ped and vehicular entrance from broadway.interior renovation and relocate of elevator. rev to pa201602028565.
- Filed
- Jun 13, 2025
- Issued
- May 27, 2026 (11 months after filing)
- Completed
- Not completed yet
- Review stops
- 43 stops across 7 departments
- Comments issued
- 11 times, by Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | May 28, 2025 | Jun 11, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 13, 2025 | Jun 13, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jun 13, 2025 | Jun 24, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jun 13, 2025 | Aug 12, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jun 13, 2025 | Aug 15, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 13, 2025 | Aug 6, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 13, 2025 | Jun 17, 2025 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Jun 13, 2025 | Jun 16, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jun 13, 2025 | Jun 25, 2025 | Approved |
Public Health HEALTH-MH | Jun 13, 2025 | Jun 16, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Jun 13, 2025 | Jan 5, 2026 | Administrative |
Urban forestry Public Works · DPW-BUF | Jun 17, 2025 | Jul 15, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Jul 15, 2025 | Jul 15, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 26, 2025 | Oct 3, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 26, 2025 | Oct 6, 2025 | Issued Comments |
Mechanical plan review quality control Building Inspection · MECH-QC | Oct 3, 2025 | Oct 3, 2025 | Approved |
Building plan review Building Inspection · BLDG | Oct 9, 2025 | Oct 23, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Oct 9, 2025 | Oct 9, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 9, 2025 | Oct 14, 2025 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Oct 9, 2025 | Oct 14, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Oct 9, 2025 | Oct 21, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 9, 2025 | Oct 14, 2025 | Approved |
Public Health HEALTH-MH | Oct 9, 2025 | Oct 14, 2025 | Approved |
Building plan review Building Inspection · BLDG | Nov 6, 2025 | Nov 18, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Nov 6, 2025 | Nov 17, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Nov 12, 2025 | Nov 12, 2025 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Nov 14, 2025 | Nov 14, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Nov 17, 2025 | Nov 20, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 17, 2025 | Dec 4, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Nov 17, 2025 | Nov 18, 2025 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Nov 17, 2025 | Nov 24, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 17, 2025 | Nov 21, 2025 | Approved |
Public Health HEALTH-MH | Nov 17, 2025 | Nov 21, 2025 | Approved |
Building plan review Building Inspection · BLDG | Dec 2, 2025 | Dec 16, 2025 | Approved |
Zoning review Planning · CP-ZOC | Dec 16, 2025 | Dec 23, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Dec 16, 2025 | Dec 30, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Dec 16, 2025 | Dec 17, 2025 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Dec 16, 2025 | Dec 17, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Dec 16, 2025 | Dec 30, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 16, 2025 | Dec 19, 2025 | Approved |
Public Health HEALTH-MH | Dec 16, 2025 | Dec 17, 2025 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Dec 17, 2025 | Dec 17, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 5, 2026 | May 27, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $3,542,204
| Name | Role | License on permit |
|---|---|---|
| Joshua Gary Larson Larson Shores Architects | Architect | C-30627 |
| Benjamin Pan-Hon Lai Benjamin Lai & Associates | Engineer | 3268 |
| Denny Chi-Ho Kwan Holmes Culley | Engineer | S4887 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025