595 Alabama St
San Francisco permit 202505297530 · Mission
Construction of 1 partial height wall. installation of 1 traffic gate. new seating and tables. refinish floor in area of work. legalize the e roll down doors along the alabama st and 18th frontages under planning code section 145.1 d3a to abate envorcement case 2022012702 enf
- Filed
- May 29, 2025
- Issued
- Jul 21, 2025 (2 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2025 were typically issued within 1 month (median of 5,178 issued permits).
- Review stops
- 15 stops across 5 departments
- Comments issued
- 3 times, by Planning, Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | May 29, 2025 | May 29, 2025 | Administrative |
Zoning review Planning · CP-ZOC | May 30, 2025 | May 30, 2025 | Issued Comments |
Intake Building Inspection · INTAKE | Jun 17, 2025 | Jun 17, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jun 17, 2025 | Jun 17, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jun 18, 2025 | Jun 18, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Jun 20, 2025 | Jun 20, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 20, 2025 | Jun 20, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jun 20, 2025 | Jun 20, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jun 20, 2025 | Jun 20, 2025 | Not Applicable |
Building plan review Building Inspection · BLDG | Jul 16, 2025 | Jul 16, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jul 16, 2025 | Jul 16, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jul 18, 2025 | Jul 18, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 18, 2025 | Jul 18, 2025 | Approved |
Public health review Public Health · HEALTH | Jul 18, 2025 | Jul 18, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 21, 2025 | Jul 21, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Issued
- Estimated cost
- $12,500
| Name | Role | License on permit |
|---|---|---|
| Terryl Marshall Lofrano Lofrano Architecture | Architect | C7292 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026