425 Diamond St
San Francisco permit 202505307607 · Noe Valley
No work @ basement & 1st floor. demolish (e) bathroom @ rear facade. new single story horizontal addion for living room @ rear facade. add bathroom & closet to the offce on 2nd floor. interior renovation of bedroom on 3rd floor. add bathroom, closet & dryer/washer on 3rd floor. replace windows &
- Filed
- Jun 11, 2025
- Issued
- Feb 17, 2026 (8 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 30 stops across 5 departments
- Comments issued
- 12 times, by Building Inspection, Fire Department, Public Utilities, Planning
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | May 27, 2025 | Jun 10, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | May 30, 2025 | Jun 11, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jun 12, 2025 | Jun 12, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jun 12, 2025 | Aug 11, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jun 12, 2025 | Aug 8, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 12, 2025 | Jul 20, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 12, 2025 | Jun 13, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jun 12, 2025 | Jun 26, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Jun 12, 2025 | Dec 1, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Aug 22, 2025 | Sep 5, 2025 | Issued Comments |
Building plan review quality control Building Inspection · BLDG-QC | Sep 5, 2025 | Sep 5, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 12, 2025 | Sep 12, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Sep 15, 2025 | Sep 22, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 18, 2025 | Oct 17, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 18, 2025 | Sep 18, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Sep 23, 2025 | Sep 23, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Sep 26, 2025 | Oct 2, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 27, 2025 | Oct 28, 2025 | Approved |
Zoning review Planning · CP-ZOC | Oct 28, 2025 | Oct 28, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 28, 2025 | Oct 28, 2025 | Approved-Stipulated |
Mechanical and energy plan review Building Inspection · MECH | Oct 30, 2025 | Oct 30, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Nov 3, 2025 | Nov 3, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Nov 7, 2025 | Nov 7, 2025 | Approved |
Zoning review Planning · CP-ZOC | Nov 10, 2025 | Nov 17, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 12, 2025 | Nov 12, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Nov 12, 2025 | Nov 12, 2025 | Approved-Stipulated |
Building plan review Building Inspection · BLDG | Nov 13, 2025 | Nov 13, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Nov 14, 2025 | Nov 17, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 18, 2025 | Dec 1, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 1, 2025 | Feb 17, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $292,013
| Name | Role | License on permit |
|---|---|---|
| Abraham Jayson Jayson Architecture | Architect | C33239 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2016