3829 25th St
San Francisco permit 202506037833 · Noe Valley
Add lower level dwelling unit. veritical addition to add 3rd story; add rooftop terrace. remove and replace front stair and 2nd level entry.
- Filed
- Jun 25, 2025
- Issued
- Dec 2, 2025 (5 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 21 stops across 6 departments
- Comments issued
- 6 times, by Planning, Building Inspection, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | May 29, 2025 | Jun 17, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 23, 2025 | Jun 23, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jun 23, 2025 | Jun 25, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Jun 23, 2025 | Jul 10, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jun 23, 2025 | Jul 10, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 23, 2025 | Jun 28, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 23, 2025 | Jun 25, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jun 23, 2025 | Jul 3, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Jun 23, 2025 | Jul 16, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 23, 2025 | Jul 2, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Jun 23, 2025 | Oct 14, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Sep 8, 2025 | Sep 8, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 9, 2025 | Sep 9, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Sep 9, 2025 | Sep 9, 2025 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Sep 12, 2025 | Sep 15, 2025 | Approved |
Building plan review Building Inspection · BLDG | Sep 26, 2025 | Sep 26, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Sep 26, 2025 | Sep 26, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Sep 26, 2025 | Oct 6, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 26, 2025 | Oct 3, 2025 | Approved |
Development fee collection Building Inspection · DFCU | Oct 6, 2025 | Oct 6, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Oct 14, 2025 | Dec 2, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Suspend
- Estimated cost
- $995,900
| Name | Role | License on permit |
|---|---|---|
| Troy A Kashanipour Troy Kashanipour | Architect | C27646 |
| Joe Terhemen Igber Sedr Consulting | Engineer | C78132 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025