2762 21st St
San Francisco permit 202506037843 · Mission
Remodel of entire house and a 2nd story addition with front and rear roof decks on 2nd level.
- Filed
- Jun 24, 2025
- Issued
- Feb 9, 2026 (8 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 23 stops across 6 departments
- Comments issued
- 4 times, by Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | May 30, 2025 | Jun 16, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 25, 2025 | Jun 25, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jun 25, 2025 | Jan 21, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jun 25, 2025 | Aug 10, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jun 25, 2025 | Aug 8, 2025 | Not Applicable |
Mechanical and energy plan review Building Inspection · MECH | Jun 25, 2025 | Jul 21, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 25, 2025 | Jul 1, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 25, 2025 | Jul 3, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Jun 25, 2025 | Aug 8, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 25, 2025 | Jul 2, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Jun 25, 2025 | Jan 22, 2026 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Sep 26, 2025 | Oct 3, 2025 | Approved |
Building plan review Building Inspection · BLDG | Oct 3, 2025 | Oct 27, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Oct 16, 2025 | Oct 16, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Oct 20, 2025 | Oct 28, 2025 | Approved |
Building plan review Building Inspection · BLDG | Nov 6, 2025 | Nov 6, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 19, 2025 | Nov 19, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 7, 2026 | Jan 14, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jan 7, 2026 | Jan 9, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Jan 7, 2026 | Jan 21, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 7, 2026 | Jan 8, 2026 | Approved |
Development fee collection Building Inspection · DFCU | Jan 21, 2026 | Jan 22, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jan 22, 2026 | Feb 9, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $852,477
| Name | Role | License on permit |
|---|---|---|
| Antje Paiz Raumfabrik | Architect | C-31989 |
| Peter David Bonneau Pe Structural Design | Engineer | C81545 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2025