5 Montague Pl
San Francisco permit 202506047906 · North Beach
New roof deck. int & ext stairs for roof deck access. new skylights, fire rated. parapets & roof stair / deck guards. expand garge to include storage / mech rooms. new garage conc floor slab, foundation upgrades. new garage door & rear facade sliding doors. lower (e) rear patio on grade. relocate /
- Filed
- Jun 4, 2025
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 11 stops across 5 departments
- Comments issued
- Once, by Permit Center
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jun 2, 2025 | Jun 20, 2025 | Issued Comments |
Central Permit Bureau Building Inspection · CPB | Jun 5, 2025 | In progress | In Progress |
Permit Center Permit Center · PERMIT-CTR | Jul 7, 2025 | Jul 15, 2025 | Approved |
Zoning review Planning · CP-ZOC | — | In progress | — |
Building plan review Building Inspection · BLDG | — | In progress | — |
Structural plan approval Building Inspection · PAD-STR | — | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | — | In progress | — |
Fire prevention review Fire Department · SFFD | — | In progress | — |
Public Utilities Commission review Public Utilities · SFPUC | — | In progress | — |
Permit Processing Center Building Inspection · PPC | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Triage
- Estimated cost
- $334,000
| Name | Role | License on permit |
|---|---|---|
| Dennis C Budd Dennis Budd Aia Architect | Architect | C26969 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Aug 2014