CheckMyDesigner

629 Post St

San Francisco permit 202506057967 · Tenderloin

Seismic retrofit or foundationFull plan reviewIssued
Street view · Sep 2026
Google Street View of 629 Post St, Sep 2026
Scope of work
As written on the permit application.

Ed 13-01:bsmt,1/f upgrades to offices/common area;elevator to bsmt.alt (e) entrances for ada; voluntary seismic upgrades, soft story retro.alt 1/f residences:20 of 63 units upgrade w/ (n) cooking area. limited ceiling r/r in-kind for floor ties passthrough for seismic upgrade.

Timeline
Key dates from the city record.
Filed
Jun 5, 2025
Issued
Jan 6, 2026 (7 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
41 stops across 7 departments
Comments issued
18 times, by Building Inspection, Fire Department, Public Works, Public Utilities, Public Health
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Jun 16, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Jun 17, 2025Administrative

Zoning review

Planning · CP-ZOC

Jun 18, 2025Approved

Building plan review

Building Inspection · BLDG

Jul 30, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Jul 28, 2025Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jun 28, 2025Issued Comments

Electrical plan review

Building Inspection · MECH-E

Jun 25, 2025Issued Comments

Fire Department housing review

Fire Department · SFFD-HQ

Jul 9, 2025Issued Comments

Street use and mapping

Public Works · DPW-BSM

Jun 18, 2025Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Jul 8, 2025Issued Comments

Permit Processing Center

Building Inspection · PPC

Dec 29, 2025Administrative

Public health review

Public Health · HEALTH

Jul 28, 2025Administrative

Public health food review

Public Health · HEALTH-FD

Jul 31, 2025Issued Comments

Building plan review

Building Inspection · BLDG

Sep 8, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Sep 5, 2025Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Sep 10, 2025Approved

Electrical plan review

Building Inspection · MECH-E

Aug 26, 2025Issued Comments

Street use and mapping

Public Works · DPW-BSM

Aug 28, 2025Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Aug 28, 2025Issued Comments

Building plan review

Building Inspection · BLDG

Sep 3, 2025Not Applicable

Fire Department housing review

Fire Department · SFFD-HQ

Sep 9, 2025Issued Comments

Street use and mapping

Public Works · DPW-BSM

Sep 17, 2025Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Dec 1, 2025Issued Comments

Street use and mapping

Public Works · DPW-BSM

Nov 6, 2025Approved

Electrical plan review

Building Inspection · MECH-E

Nov 7, 2025Issued Comments

Public health food review

Public Health · HEALTH-FD

Nov 7, 2025Approved

Building plan review

Building Inspection · BLDG

Nov 17, 2025Approved

Structural plan approval

Building Inspection · PAD-STR

Nov 23, 2025Approved

Fire Department housing review

Fire Department · SFFD-HQ

Nov 18, 2025Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Dec 9, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Dec 17, 2025Approved

Zoning review

Planning · CP-ZOC

Dec 17, 2025Approved

Building plan review

Building Inspection · BLDG

Dec 18, 2025Approved

Structural plan approval

Building Inspection · PAD-STR

Dec 24, 2025Approved

Electrical plan review

Building Inspection · MECH-E

Dec 17, 2025Approved

Fire Department housing review

Fire Department · SFFD-HQ

Dec 17, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Dec 22, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Dec 22, 2025Approved

Public health food review

Public Health · HEALTH-FD

Dec 19, 2025Approved

Zoning review

Planning · CP-ZOC

Dec 17, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Jan 6, 2026Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$12,000,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Michelle Anne Sullivan

Ssdp

ArchitectC-25093
Ryan Bogart

Zfa Structural Engineers

EngineerS6104
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202506057967 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record