552 Folsom St
San Francisco permit 202506068152 · Financial District/South Beach
Proj-25-0616: under ramp park: construct 2-story, type 5b, office/ assembly b & a-2
- Filed
- Jul 23, 2025
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 30 stops across 8 departments
- Comments issued
- 9 times, by Permit Center, Building Inspection, Fire Department, Public Works, Public Health
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jun 2, 2025 | Jun 17, 2025 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Jul 3, 2025 | Jul 23, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 23, 2025 | Jul 23, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jul 23, 2025 | Jul 29, 2025 | Not Applicable |
Redevelopment review Redevelopment · REDEV | Jul 23, 2025 | In progress | — |
Building plan review Building Inspection · BLDG | Jul 23, 2025 | Sep 2, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jul 23, 2025 | Sep 4, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 23, 2025 | Aug 15, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Jul 23, 2025 | Jul 31, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jul 23, 2025 | Oct 2, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jul 23, 2025 | Jul 24, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Jul 23, 2025 | Sep 11, 2025 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Jul 23, 2025 | Aug 6, 2025 | Approved |
Public Utilities programs review Public Utilities · SFPUC-PRG | Jul 23, 2025 | Aug 11, 2025 | Approved-Stipulated |
Public health review Public Health · HEALTH | Jul 23, 2025 | Jul 23, 2025 | Administrative |
Public health food review Public Health · HEALTH-FD | Jul 23, 2025 | Jul 23, 2025 | — |
Public Health HEALTH-MH | Jul 23, 2025 | Jul 24, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Jul 23, 2025 | In progress | — |
Street use and mapping Public Works · DPW-BSM | Sep 4, 2025 | Sep 11, 2025 | Approved-Stipulated |
Public Works disability access review Public Works · PW-DAC | Sep 16, 2025 | Sep 16, 2025 | Issued Comments |
Address verification Building Inspection · ADDR | — | In progress | — |
Building plan review Building Inspection · BLDG | — | In progress | — |
Structural plan approval Building Inspection · PAD-STR | — | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | — | In progress | — |
Electrical plan review Building Inspection · MECH-E | — | In progress | — |
Fire prevention review Fire Department · SFFD | — | In progress | — |
Public Works disability access review Public Works · PW-DAC | — | In progress | — |
Public Health HEALTH-MH | — | In progress | — |
Development fee collection Building Inspection · DFCU | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction wood frame
- Status
- Filed
- Estimated cost
- $5,000,000
| Name | Role | License on permit |
|---|---|---|
| Yakuh Django Askew Ya Studio | Architect | 29776 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026