361 Upper Tr
San Francisco permit 202506098196 · Haight Ashbury
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Revision to pa #202201135971 for reduction in scope, project to proceed with placing of windows,doors, nw balcony guardrails, select demo of interior walls less than 25%. enlarged opening of level 01 windows, replace interior stair, spiral stair down to back yard. approx. 90% reduction in app. scp
- Filed
- Aug 14, 2025
- Issued
- Jan 14, 2026 (5 months after filing)
- Completed
- Sep 23, 2026 (8 months after issuance)
- Review stops
- 22 stops across 5 departments
- Comments issued
- 5 times, by Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jun 9, 2025 | Jun 9, 2025 | Administrative |
Intake Building Inspection · INTAKE | Jul 10, 2025 | Jul 10, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jul 10, 2025 | Jul 10, 2025 | Approved |
Permit Center Permit Center · PERMIT-CTR | Aug 1, 2025 | Aug 13, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 14, 2025 | Aug 15, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Aug 15, 2025 | Sep 18, 2025 | Approved |
Building plan review Building Inspection · BLDG | Aug 15, 2025 | Sep 22, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Aug 15, 2025 | Sep 18, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Aug 15, 2025 | Sep 11, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 15, 2025 | Aug 18, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Aug 15, 2025 | Aug 20, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Aug 15, 2025 | Jan 8, 2026 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Oct 24, 2025 | Nov 3, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Oct 28, 2025 | Oct 28, 2025 | Approved-Stipulated |
Building plan review Building Inspection · BLDG | Nov 7, 2025 | Nov 7, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 3, 2025 | Dec 3, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Dec 17, 2025 | Dec 17, 2025 | Approved |
Building plan review Building Inspection · BLDG | Dec 17, 2025 | Dec 17, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 17, 2025 | Jan 7, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Dec 17, 2025 | Dec 18, 2025 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Dec 17, 2025 | Dec 18, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 8, 2026 | Jan 14, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $16,500
| Name | Role | License on permit |
|---|---|---|
| Kevin Hugo Zeller Zero Ten Design | Authorized agent-others | C32204 |
| David Benjamin Yadegar David Yadegar, Pe | Engineer | C73922 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2020