166 Landers St
San Francisco permit 202506118437 · Castro/Upper Market
Build horizontal extension to the rear of the (e) ground floor and second floors. build a vertical extension (3rd floor addition) avove the seond floor. preserve the (e) front facade and front exterior stairs. remodel and renovate interior spaces to both (e) floors. build an on grade patio at the
- Filed
- Jul 24, 2025
- Issued
- Feb 5, 2026 (6 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 31 stops across 6 departments
- Comments issued
- 3 times, by Building Inspection, Public Works
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jun 10, 2025 | Jun 17, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 25, 2025 | Jul 24, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jul 24, 2025 | Aug 4, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jul 24, 2025 | Aug 6, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jul 24, 2025 | Aug 14, 2025 | Not Applicable |
Fire prevention review Fire Department · SFFD | Jul 24, 2025 | Jul 25, 2025 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Jul 24, 2025 | Aug 4, 2025 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Jul 24, 2025 | Aug 27, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 24, 2025 | Jul 31, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Jul 24, 2025 | Jan 23, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jan 9, 2026 | Jan 10, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 9, 2026 | Jan 15, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jan 9, 2026 | Jan 21, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Jan 9, 2026 | Jan 12, 2026 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Jan 9, 2026 | Jan 23, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 9, 2026 | Jan 13, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 23, 2026 | Feb 5, 2026 | Administrative |
Addendum 1: Foundation & superstructure (structural).
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Feb 6, 2026 | Feb 20, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 10, 2026 | Feb 24, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Feb 24, 2026 | Apr 17, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Feb 24, 2026 | Apr 16, 2026 | Not Applicable |
Fire prevention review Fire Department · SFFD | Feb 24, 2026 | Mar 2, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Feb 24, 2026 | Feb 25, 2026 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Feb 24, 2026 | Apr 7, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Feb 24, 2026 | Jun 1, 2026 | Administrative |
Street use and mapping Public Works · DPW-BSM | Mar 19, 2026 | Mar 19, 2026 | Approved |
Building plan review Building Inspection · BLDG | May 19, 2026 | May 22, 2026 | Approved |
Fire prevention review Fire Department · SFFD | May 19, 2026 | May 20, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | May 19, 2026 | May 21, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | May 19, 2026 | May 29, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 1, 2026 | Jun 8, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $1,357,599
| Name | Role | License on permit |
|---|---|---|
| Juancho Cueto Jr Isidoro I-Design Architecture | Architect | C39427 |
| Donald David Double D Engineering | Engineer | S3928 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026