**ab-004** site permit with shared plans for 202506128526 to include new foundation for (n) community facility on the east side of caroline st and 138 ft from north mariposa st.
- Filed
- Oct 7, 2025
- Issued
- Apr 7, 2026 (6 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 30 stops across 7 departments
- Comments issued
- 9 times, by Permit Center, Building Inspection, Fire Department, Public Works, Public Utilities, Public Health
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jun 11, 2025 | Jun 25, 2025 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Aug 18, 2025 | Sep 4, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 7, 2025 | Oct 7, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Oct 7, 2025 | Oct 8, 2025 | Approved |
Building plan review Building Inspection · BLDG | Oct 7, 2025 | Oct 28, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 7, 2025 | Jan 3, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Oct 7, 2025 | Oct 9, 2025 | Approved-Stipulated |
Public Works disability access review Public Works · PW-DAC | Oct 7, 2025 | Oct 29, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Oct 7, 2025 | Oct 27, 2025 | Issued Comments |
Public Utilities programs review Public Utilities · SFPUC-PRG | Oct 7, 2025 | Oct 27, 2025 | Approved |
Public Health HEALTH-MH | Oct 7, 2025 | Oct 9, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Oct 7, 2025 | Mar 13, 2026 | Administrative |
Building plan review quality control Building Inspection · BLDG-QC | Oct 27, 2025 | Oct 27, 2025 | Approved |
Zoning review Planning · CP-ZOC | Dec 23, 2025 | Dec 23, 2025 | Approved |
Building plan review Building Inspection · BLDG | Dec 23, 2025 | Jan 6, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Dec 23, 2025 | Dec 30, 2025 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Dec 23, 2025 | Feb 20, 2026 | Approved-Stipulated |
Public Works disability access review Public Works · PW-DAC | Dec 23, 2025 | Jan 7, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Dec 23, 2025 | Dec 26, 2025 | Issued Comments |
Public Utilities programs review Public Utilities · SFPUC-PRG | Dec 23, 2025 | Dec 23, 2025 | Approved |
Public Health HEALTH-MH | Dec 23, 2025 | Dec 31, 2025 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Dec 31, 2025 | Dec 31, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 6, 2026 | Jan 16, 2026 | Not Applicable |
Building plan review quality control Building Inspection · BLDG-QC | Jan 14, 2026 | Jan 14, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 15, 2026 | Jan 15, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jan 20, 2026 | Jan 20, 2026 | Approved |
Public Works disability access review Public Works · PW-DAC | Jan 26, 2026 | Jan 26, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Feb 20, 2026 | Feb 20, 2026 | Approved-Stipulated |
Development fee collection Building Inspection · DFCU | Feb 20, 2026 | Mar 5, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | Mar 13, 2026 | Apr 7, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction wood frame
- Status
- Issued
- Estimated cost
- $425,000
| Name | Role | License on permit |
|---|---|---|
| Brian H Liles Jackson Liles Architecture | Architect | C-27249 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026