520 Oak Park Dr
San Francisco permit 202506128536 · Inner Sunset
Site permit- create a new entrance to existing suite by adding the existing porch area. change tiles, floor, toilet and sink at existing suite bathroom. add radiant heating floor @ suite
- Filed
- Jul 3, 2025
- Issued
- Jul 10, 2026 (12 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 37 stops across 5 departments
- Comments issued
- 6 times, by Building Inspection, Public Utilities, Permit Center
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jun 11, 2025 | Jun 27, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 7, 2025 | Jul 7, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jul 7, 2025 | Jul 31, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jul 7, 2025 | Aug 6, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jul 7, 2025 | Aug 18, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jul 7, 2025 | Jul 15, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 7, 2025 | Jul 9, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Jul 7, 2025 | Apr 9, 2026 | Administrative |
Building plan review quality control Building Inspection · BLDG-QC | Aug 6, 2025 | Aug 6, 2025 | Approved |
Zoning review Planning · CP-ZOC | Feb 2, 2026 | Mar 4, 2026 | Approved |
Building plan review Building Inspection · BLDG | Feb 2, 2026 | Feb 9, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Feb 2, 2026 | Feb 13, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Feb 2, 2026 | Feb 9, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 2, 2026 | Feb 3, 2026 | Approved |
Building plan review Building Inspection · BLDG | Feb 17, 2026 | Mar 2, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Feb 17, 2026 | Mar 30, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Feb 17, 2026 | Feb 23, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 17, 2026 | Feb 18, 2026 | Approved |
Zoning review Planning · CP-ZOC | Mar 18, 2026 | Apr 9, 2026 | Approved |
Building plan review Building Inspection · BLDG | Mar 18, 2026 | Mar 24, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Mar 18, 2026 | Mar 20, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 18, 2026 | Mar 19, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Mar 24, 2026 | Mar 24, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 9, 2026 | Jul 10, 2026 | Administrative |
Addendum 1: Architectural/structural
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jul 14, 2026 | Aug 4, 2026 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Aug 11, 2026 | Aug 24, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 24, 2026 | Sep 4, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Sep 4, 2026 | In progress | — |
Building plan review Building Inspection · BLDG | Sep 4, 2026 | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | Sep 4, 2026 | Oct 2, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 4, 2026 | Sep 9, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 4, 2026 | Sep 9, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Sep 4, 2026 | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | Oct 21, 2026 | Oct 30, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Oct 21, 2026 | Oct 22, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 21, 2026 | Oct 22, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $70,000
| Name | Role | License on permit |
|---|---|---|
| Carlos Renan Dominguez | Architect | C26949 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Aug 2015