Scope of work
As written on the permit application.

To comply to nov# 202423971 to include expansion of roof deck, expansion of bedroom #1, install security gate at roof deck ladder. ref pa# 201306189882 & pa# 201603222778.

Timeline
Key dates from the city record.
Filed
Jul 16, 2025
Issued
Aug 10, 2026 (13 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
24 stops across 4 departments
Comments issued
7 times, by Permit Center, Building Inspection, Fire Department, Planning
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Jun 27, 2025Issued Comments

Permit Center

Permit Center · PERMIT-CTR

Jul 16, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Jul 17, 2025Administrative

Zoning review

Planning · CP-ZOC

Jul 22, 2025Approved

Building plan review

Building Inspection · BLDG

Sep 4, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Sep 4, 2025Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Aug 13, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

Jul 17, 2025Issued Comments

Building inspector

Building Inspection · BID-INSP

Jun 16, 2026Approved

Permit Processing Center

Building Inspection · PPC

Jun 24, 2026Administrative

Fire prevention review

Fire Department · SFFD

Jul 25, 2025Approved

Mechanical plan review quality control

Building Inspection · MECH-QC

Aug 12, 2025Approved

Building plan review quality control

Building Inspection · BLDG-QC

Sep 4, 2025Administrative

Building plan review

Building Inspection · BLDG

Jun 12, 2026Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Jun 16, 2026Approved

Fire prevention review

Fire Department · SFFD

Jun 8, 2026Approved-Stipulated

Fire prevention review

Fire Department · SFFD

Jun 10, 2026Administrative

Building plan review

Building Inspection · BLDG

Jun 16, 2026Approved

Mechanical and energy plan review

Building Inspection · MECH

Jun 17, 2026Approved

Fire prevention review

Fire Department · SFFD

Jun 18, 2026Approved-Stipulated

Zoning review

Planning · CP-ZOC

Jun 23, 2026Issued Comments

Fire prevention review

Fire Department · SFFD

Jun 22, 2026Administrative

Zoning review

Planning · CP-ZOC

Jun 23, 2026Approved

Central Permit Bureau

Building Inspection · CPB

Aug 10, 2026Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$25,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Andrew Ross Levine

Levine Architects

Architect14090
Sources