419 21st Av
San Francisco permit 202506128552 · Outer Richmond
Revision or supplementOver-the-counter, with plansComplete
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Scope of work
As written on the permit application.
Revision to pa# 202503192576: add footing at office room per plan for unit # 419
Timeline
Key dates from the city record.
- Filed
- Jun 12, 2025
- Issued
- Jun 17, 2025 (within 1 month of filing)
- Completed
- Feb 24, 2026 (8 months after issuance)
City plan review
Each review stop the plans went through, from the city's routing record.
- Review stops
- 3 stops across 1 department
- Comments issued
- None
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jun 12, 2025 | Jun 12, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Jun 12, 2025 | Jun 12, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 17, 2025 | Jun 17, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
Permit details
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $8,000
People named on this permit
Only people we matched to a California license are listed.
| Name | Role | License on permit |
|---|---|---|
| Yanxian Chen | Engineer | C94212 |
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202506128552 on the city's permit tracking site
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025